Courseiva
Project Management Concepts →mediumMultiple Choice

PK0-005 Project Management Concepts Practice Question

An organization is evaluating two potential projects. Project A has an NPV of $50,000 and a payback period of 2 years. Project B has an NPV of $40,000 and a payback period of 1.5 years. The organization's policy is to select projects with the highest NPV. Which project should be selected?

⚠ Common exam trap

The trap is that Project B's shorter payback period looks attractive and tempts candidates to override the stated policy; the exam tests whether you follow the explicit decision criterion (highest NPV) rather than substituting your own judgment.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Project A because it has a higher NPV

The organization's stated policy is to select the project with the highest NPV, and Project A has an NPV of $50,000 versus Project B's $40,000. Therefore Project A should be selected because it delivers greater net present value, which is the decision criterion the policy mandates.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Project A because it has a higher NPV

    Why this is correct

    The organisation's stated policy selects the project with the highest net present value, so Project A's $50,000 NPV outranks Project B's $40,000. Payback period is a secondary liquidity measure and does not override the mandated NPV criterion.

  • ✗

    Project A because it has a longer payback period

    Why it's wrong here

    Payback period measures how quickly investment is recovered, not total value created; policy mandates highest NPV, and Project A already wins on that $50,000 figure. Selecting it for a longer payback period inverts the stated criterion. Payback period is decisive only when liquidity or risk-recovery speed is the governing constraint.

  • ✗

    Project B because it has a shorter payback period

    Why it's wrong here

    The payback period measures how quickly investment is recovered, but the policy explicitly ranks projects by NPV. Project B's $40,000 NPV is below Project A's $50,000, so it fails the stated criterion. Project B would be correct only if the selection policy used payback period.

  • ✗

    Project B because it has a lower NPV

    Why it's wrong here

    Project B's NPV is $40,000, lower than Project A's $50,000, so selecting it contradicts the stated policy of choosing the highest NPV. The shorter payback period is irrelevant under that policy. Project B would be correct if the organisation prioritised fastest capital recovery instead.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 954 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.