A project sponsor asks the project manager to accelerate the schedule. Which TWO schedule compression techniques could the project manager consider?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Fast-tracking
Fast-tracking and crashing are the two primary schedule compression techniques.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Fast-tracking
Why this is correct
Fast-tracking overlaps sequential activities, compressing the schedule but increasing risk.
- ✓
Crashing
Why this is correct
Crashing adds resources to critical path activities, compressing the schedule but increasing cost.
- ✗
Monte Carlo simulation
Why it's wrong here
Monte Carlo simulation is a risk analysis technique, not a schedule compression technique.
- ✗
Resource leveling
Why it's wrong here
Resource leveling adjusts the schedule to address resource constraints, often lengthening it.
- ✗
Scope reduction
Why it's wrong here
Scope reduction is not a schedule compression technique; it changes the project scope.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.