PK0-005 Project Management Concepts Practice Question

In which project life cycle phase are project risks identified and a risk management plan created?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Planning

Risk identification and planning occur during the planning phase.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Planning

    Why this is correct

    The planning phase includes risk management planning.

  • Closing

    Why it's wrong here

    Closing includes finalizing and lessons learned, not initial risk identification.

  • Initiating

    Why it's wrong here

    Initiating focuses on authorization; detailed planning occurs later.

  • Executing

    Why it's wrong here

    Executing is when work is done; risks are monitored but identified earlier.

About these practice questions

One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.