PK0-005 Practice Question: A project manager is leading a software…
A project manager is leading a software development project. The client requests a feature change that will add two weeks to the schedule and increase costs by $10,000. The project manager evaluates the impact and presents options to the change control board. The board approves the change but the project sponsor expresses concern about the budget. What should the project manager do next?
⚠ Common exam trap
Many candidates confuse the sponsor's concern with a veto power, but the CCB has final authority over change approval; the PM's duty is to implement the decision and manage stakeholder expectations, not to re-open the decision.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Update the project management plan and baseline to reflect the change
The change control board (CCB) has approved the change, making it an authorized modification. The project manager must now update the project management plan and baseline to formally incorporate the approved change, ensuring the schedule and budget reflect the new scope. The sponsor's concern is noted but does not override the CCB's decision; the PM should address the concern through communication and reporting, not by halting the process.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Cancel the change until the sponsor is satisfied
Why it's wrong here
The change is approved; cancellation would require a new change request.
- ✓
Update the project management plan and baseline to reflect the change
Why this is correct
After approval, the plans and baselines must be updated.
- ✗
Proceed with the original plan and ignore the sponsor's concern
Why it's wrong here
The change is approved, so the plan must be updated.
- ✗
Escalate the sponsor's concern to the change control board
Why it's wrong here
The change is already approved; escalation is unnecessary.
Go deeper
Related to this question
About these practice questions
One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.