PK0-005 Tools and Documentation Practice Question
A project manager is creating a document that formally authorizes the project and assigns the project manager. Which document is this?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Project charter
The project charter is the document that formally authorizes a project and provides the project manager with authority to apply organizational resources.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Risk register
Why it's wrong here
A risk register logs identified risks, their probability, impact, and responses; it grants no authority and names no project manager. The project charter is the authorising document. A risk register would be correct once the project is chartered and the team is recording and tracking threats to objectives.
- ✓
Project charter
Why this is correct
The project charter is the formal authorisation document that names the project manager and grants them authority to apply organisational resources. It satisfies the stem's requirement for both formal authorisation and assignment of the project manager, distinguishing it from the project management plan.
- ✗
Project management plan
Why it's wrong here
The project management plan describes how the project will be executed, monitored, and closed; it is produced after authorisation, not the document that grants it. The project charter formally authorises the project and assigns the manager. A project management plan would be correct when baselining scope, schedule, and cost for an approved project.
- ✗
WBS
Why it's wrong here
A WBS decomposes project scope into deliverables and work packages; it neither authorises the project nor names the project manager. The project charter performs both. A WBS would be the right artefact when the charter exists and the team needs to break scope into manageable, estimable components for scheduling.
About these practice questions
This PK0-005 question is part of Courseiva's 954-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.