Courseiva
Tools and DocumentationeasyMultiple ChoiceObjective-mapped

PK0-005 Tools and Documentation Practice Question

A project manager is creating a document that formally authorizes the project and assigns the project manager. Which document is this?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Project charter

The project charter is the document that formally authorizes a project and provides the project manager with authority to apply organizational resources.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Risk register

    Why it's wrong here

    Risk register lists risks, not authorization.

  • Project charter

    Why this is correct

    Correct; charter authorizes the project.

  • Project management plan

    Why it's wrong here

    The plan describes how the project will be executed, not authorization.

  • WBS

    Why it's wrong here

    WBS breaks down work, not authorization.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.