PK0-005 Project Life Cycle Practice Question
A project team is experiencing conflicts and power struggles among members. According to Tuckman's stages of group development, which stage is the team likely in?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Storming
In the storming stage, team members may have differing opinions, leading to conflicts and power struggles as they assert themselves.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Performing
Why it's wrong here
Performing is high-functioning with minimal conflict.
- ✓
Storming
Why this is correct
Storming involves conflict, power struggles, and resistance to group influence.
- ✗
Forming
Why it's wrong here
Forming is characterized by politeness and orientation, not conflict.
- ✗
Norming
Why it's wrong here
Norming is when the team starts to resolve differences and agree on norms.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.