PK0-005 Tools and Documentation Practice Question
A project manager is creating a document that formally authorizes the project and assigns the project manager. Which document is being created?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Project charter
The project charter is the document that formally authorizes the project and identifies the project manager.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Project management plan
Why it's wrong here
The project management plan describes how the project will be executed, monitored, and controlled; it does not authorize the project.
- ✗
Business case
Why it's wrong here
The business case provides justification but does not formally authorize the project.
- ✗
Scope statement
Why it's wrong here
The scope statement defines the project scope but does not authorize the project.
- ✓
Project charter
Why this is correct
Correct: The project charter authorizes the project and assigns the project manager.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.