An organization has multiple projects that are not directly related but are all aimed at achieving the company's strategic goal of expanding into new markets. Which term best describes this collection?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Portfolio
A portfolio is a collection of projects, programs, and operational work managed as a group to achieve strategic objectives. It may contain unrelated initiatives.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Operation
Why it's wrong here
Operations are ongoing activities, not a collection of projects.
- ✗
Project
Why it's wrong here
A single project is a temporary endeavor, not a collection.
- ✓
Portfolio
Why this is correct
Correct. A portfolio aligns with strategic goals and may contain unrelated projects.
- ✗
Program
Why it's wrong here
A program is a group of related projects managed together.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.