PK0-005 Project Management Concepts Practice Question
Which TWO of the following are characteristics of a project? (Select TWO).
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Produces a unique product or service
A project is temporary (definite start and end) and creates a unique product or service. Ongoing operations are not projects. Predictive methodology is not a defining characteristic; it's an approach.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Produces the same result each time
Why it's wrong here
Projects are unique.
- ✓
Produces a unique product or service
Why this is correct
Projects create unique deliverables.
- ✓
Temporary with a definite start and end
Why this is correct
Projects are temporary.
- ✗
Uses a predictive methodology
Why it's wrong here
Not all projects use predictive; agile is also possible.
- ✗
Ongoing and repetitive
Why it's wrong here
That describes operations.
Go deeper
Related to this question
About these practice questions
One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.