Which TWO of the following are characteristics of a project? (Select TWO).

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Produces a unique product or service

A project is temporary (definite start and end) and creates a unique product or service. Ongoing operations are not projects. Predictive methodology is not a defining characteristic; it's an approach.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Produces the same result each time

    Why it's wrong here

    Projects are unique.

  • Produces a unique product or service

    Why this is correct

    Projects create unique deliverables.

  • Temporary with a definite start and end

    Why this is correct

    Projects are temporary.

  • Uses a predictive methodology

    Why it's wrong here

    Not all projects use predictive; agile is also possible.

  • Ongoing and repetitive

    Why it's wrong here

    That describes operations.

About these practice questions

One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.