PK0-005 • Practice Test 4 — 25 Questions
Free PK0-005 practice test 4 — 25 questions with explanations. No signup required.
A software development project is currently in the execution phase. The project manager has a team of 10 developers and 2 testers. The project is scheduled to be completed in 6 months, with a budget of $500,000. At the end of month 3, the project manager reviews the status and finds that only 40% of the work is complete, whereas 50% was planned. The actual cost incurred is $280,000. The project manager calculates the CPI as 0.71 and the SPI as 0.80. The project sponsor is concerned and asks for a recovery plan. The project manager must decide the best course of action. Which action should the project manager take?