Courseiva
Tools and Documentation →hardMultiple Choice

PK0-005 Tools and Documentation Practice Question

A project manager is using a control chart to monitor the number of defects per day. The chart shows 10 data points within the control limits, but all 10 points are above the mean. What does this indicate?

⚠ Common exam trap

The trap here is that candidates mistakenly believe any data point within control limits automatically means the process is stable, ignoring the run rules that detect non-random patterns like sustained shifts above or below the mean.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

A special cause variation is likely present

In a control chart, a run of 10 consecutive points above the mean (center line) is a classic indicator of a non-random pattern, even if all points fall within the control limits. This violates the 'run rule' (typically 7 or more points on one side of the mean), which signals the presence of a special cause variation that should be investigated. Option C is correct because the sustained shift above the mean suggests an assignable cause is affecting the process, not random common cause variation.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    The control limits need to be recalculated

    Why it's wrong here

    Ten consecutive points above the mean signal a non-random shift, so the limits themselves are not the fault; the process mean has moved. Recalculating limits is the right action when a documented, intentional process change has occurred and the baseline genuinely needs re-establishing, not when detecting an out-of-control run.

  • ✗

    The process is producing fewer defects than expected

    Why it's wrong here

    All ten points sit above the mean, meaning defect counts are higher than the process average, not lower. Fewer defects than expected would appear as points below the mean or a downward trend, so this reading inverts the chart's evidence.

  • ✓

    A special cause variation is likely present

    Why this is correct

    Ten consecutive points all above the mean constitute a non-random run, which control chart rules flag as special cause variation even though every point sits inside the control limits. It satisfies the stem's scenario of points within limits but consistently shifted.

  • ✗

    The process is in control and stable

    Why it's wrong here

    A run of ten points on one side of the mean is a non-random pattern indicating the process is out of control, even though every point sits inside the limits. Stability is claimed only when points vary randomly about the mean with no runs, trends or cycles present.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 954 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.