Courseiva
easyMultiple SelectObjective-mapped

PK0-005 Practice Question: Which TWO of the following activities are…

Which TWO of the following activities are typically performed during the initiation phase of a project?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Develop the project charter

Developing the project charter and identifying stakeholders are initiation phase activities. Creating the WBS, developing the schedule, and defining scope are planning phase activities.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Define project scope

    Why it's wrong here

    Scope definition is part of planning.

  • Develop the project schedule

    Why it's wrong here

    Schedule development is planning.

  • Develop the project charter

    Why this is correct

    The charter is created in initiation.

  • Create the work breakdown structure

    Why it's wrong here

    WBS creation is a planning activity.

  • Identify stakeholders

    Why this is correct

    Stakeholder identification is part of initiation.

About these practice questions

One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.