easyMultiple SelectObjective-mapped
PK0-005 Practice Question: Which TWO of the following activities are…
Which TWO of the following activities are typically performed during the initiation phase of a project?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Develop the project charter
Developing the project charter and identifying stakeholders are initiation phase activities. Creating the WBS, developing the schedule, and defining scope are planning phase activities.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Define project scope
Why it's wrong here
Scope definition is part of planning.
- ✗
Develop the project schedule
Why it's wrong here
Schedule development is planning.
- ✓
Develop the project charter
Why this is correct
The charter is created in initiation.
- ✗
Create the work breakdown structure
Why it's wrong here
WBS creation is a planning activity.
- ✓
Identify stakeholders
Why this is correct
Stakeholder identification is part of initiation.
Go deeper
Related to this question
About these practice questions
One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.