- A
Monte Carlo simulation
Why wrong: This is a modeling technique, not a compression technique.
- B
Crashing
Correct. Crashing adds resources to compress schedule while maintaining scope.
- C
Fast tracking
Why wrong: Fast tracking performs tasks in parallel, increasing risk, but also compresses schedule. However, crashing is more directly associated with adding resources.
- D
Resource leveling
Why wrong: Resource leveling often extends the schedule.
PK0-005 Project Management Concepts Practice Question
This PK0-005 practice question tests your understanding of project management concepts. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
The sponsor asks the project manager to accelerate the project schedule without changing scope. Which technique should the project manager recommend?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Crashing
Crashing is the correct technique because it involves adding additional resources to critical path activities to compress the project schedule without altering scope. This directly addresses the sponsor's request to accelerate the schedule while keeping the project scope unchanged.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Monte Carlo simulation
Why it's wrong here
This is a modeling technique, not a compression technique.
- ✓
Crashing
Why this is correct
Correct. Crashing adds resources to compress schedule while maintaining scope.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Fast tracking
Why it's wrong here
Fast tracking performs tasks in parallel, increasing risk, but also compresses schedule. However, crashing is more directly associated with adding resources.
- ✗
Resource leveling
Why it's wrong here
Resource leveling often extends the schedule.
Common exam traps
Common exam trap: answer the scenario, not the keyword
CompTIA often tests the distinction between crashing (adding resources) and fast tracking (parallel execution), where candidates mistakenly choose fast tracking because it sounds like a faster approach, but it risks rework and does not guarantee schedule compression without scope change.
Detailed technical explanation
How to think about this question
Crashing works by analyzing the cost-time tradeoff for each critical path activity, selecting those with the lowest cost slope (cost per unit time saved) to add resources. In practice, crashing may involve overtime, hiring temporary staff, or using more expensive equipment, and it is most effective when applied to activities that are not resource-constrained. A real-world scenario is a software project where adding developers to a coding task reduces duration but increases communication overhead, so the project manager must evaluate diminishing returns.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A small business has 20 workstations on the 192.168.1.0/24 network and one public IP from its ISP. The router uses PAT (NAT overload) so all 20 devices share one public address using different source ports. NAT questions test whether you understand the four address terms and which direction each translation applies.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
Project Management Concepts — study guide chapter
Learn the concepts, then practise the questions
- →
Project Management Concepts practice questions
Targeted practice on this topic area only
- →
All PK0-005 questions
500 questions across all exam domains
- →
CompTIA Project+ PK0-005 study guide
Full concept coverage aligned to exam objectives
- →
PK0-005 practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related PK0-005 practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
Project Life Cycle Phases practice questions
Practise PK0-005 questions linked to Project Life Cycle Phases.
Basics of IT Infrastructure and IT Project Management practice questions
Practise PK0-005 questions linked to Basics of IT Infrastructure and IT Project Management.
Project Management Concepts practice questions
Practise PK0-005 questions linked to Project Management Concepts.
Tools and Documentation practice questions
Practise PK0-005 questions linked to Tools and Documentation.
PK0-005 fundamentals practice questions
Practise PK0-005 questions linked to PK0-005 fundamentals.
PK0-005 scenario practice questions
Practise PK0-005 questions linked to PK0-005 scenario.
PK0-005 troubleshooting practice questions
Practise PK0-005 questions linked to PK0-005 troubleshooting.
Practice this exam
Start a free PK0-005 practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this PK0-005 question test?
Project Management Concepts — This question tests Project Management Concepts — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Crashing — Crashing is the correct technique because it involves adding additional resources to critical path activities to compress the project schedule without altering scope. This directly addresses the sponsor's request to accelerate the schedule while keeping the project scope unchanged.
What should I do if I get this PK0-005 question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Last reviewed: Jun 30, 2026
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.