A project manager is using the power/interest grid to classify stakeholders. Which group should be managed most closely because they have high power and high interest?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Manage closely

Stakeholders with high power and high interest are key players who require close management to keep them engaged and satisfied.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Keep satisfied

    Why it's wrong here

    Keep satisfied is for high power, low interest.

  • Monitor

    Why it's wrong here

    Monitor is for low power, low interest.

  • Manage closely

    Why this is correct

    Correct: high power, high interest stakeholders require close management.

  • Keep informed

    Why it's wrong here

    Keep informed is for low power, high interest.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.