A project is in the planning phase and the team is determining the sequence of activities. Which project life cycle phase follows planning?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Executing

The typical project life cycle phases are initiating, planning, executing, monitoring and controlling, and closing. Executing follows planning.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Closing

    Why it's wrong here

    Closing is the final phase.

  • Executing

    Why this is correct

    Executing comes after planning.

  • Initiating

    Why it's wrong here

    Initiating precedes planning.

  • Monitoring and controlling

    Why it's wrong here

    Monitoring and controlling occurs throughout, but not strictly after planning.

About these practice questions

One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.