PK0-005 Project Management Concepts Practice Question

Which TWO of the following are characteristics of the planning phase in the project life cycle? (Choose TWO.)

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Creating the work breakdown structure (WBS)

The planning phase involves creating detailed plans and defining scope, schedule, cost baselines.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Developing the project charter

    Why it's wrong here

    The charter is created in the initiating phase.

  • Creating the work breakdown structure (WBS)

    Why this is correct

    WBS is created during planning.

  • Delivering project deliverables

    Why it's wrong here

    Deliverables are produced during executing.

  • Performing risk identification

    Why this is correct

    Risk identification is part of planning.

  • Obtaining final acceptance

    Why it's wrong here

    Final acceptance occurs in closing.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.