A project manager receives a status report showing that the project's SPI is 0.9. What does this indicate?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
The project is behind schedule
SPI (Schedule Performance Index) = EV / PV. An SPI less than 1 means the project is behind schedule. 0.9 indicates that for every planned unit of work, only 0.9 units have been completed.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
The project is over budget
Why it's wrong here
SPI measures schedule, not cost. CPI measures cost performance.
- ✓
The project is behind schedule
Why this is correct
SPI < 1 indicates behind schedule.
- ✗
The project is on schedule
Why it's wrong here
SPI = 1 indicates on schedule.
- ✗
The project is ahead of schedule
Why it's wrong here
SPI > 1 indicates ahead of schedule.
Go deeper
Related to this question
About these practice questions
Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.