Courseiva
Project Life CycleeasyMultiple ChoiceObjective-mapped

PK0-005 Project Life Cycle Practice Question

A project manager receives a status report showing that the project's SPI is 0.9. What does this indicate?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

The project is behind schedule

SPI (Schedule Performance Index) = EV / PV. An SPI less than 1 means the project is behind schedule. 0.9 indicates that for every planned unit of work, only 0.9 units have been completed.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • The project is over budget

    Why it's wrong here

    SPI measures schedule, not cost. CPI measures cost performance.

  • The project is behind schedule

    Why this is correct

    SPI < 1 indicates behind schedule.

  • The project is on schedule

    Why it's wrong here

    SPI = 1 indicates on schedule.

  • The project is ahead of schedule

    Why it's wrong here

    SPI > 1 indicates ahead of schedule.

About these practice questions

Courseiva writes every PK0-005 question from scratch — 980 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.