PK0-005 Practice Question: A project manager is leading a construction…

A project manager is leading a construction project. The project sponsor has requested that the project be completed one month earlier than originally planned. Which THREE actions should the project manager take to assess the feasibility of this request? (Choose three.)

⚠ Common exam trap

The trap here is that candidates might incorrectly select 'Increase the project scope' (C) thinking it allows more work to be done faster, or 'Reduce quality standards' (E) as a quick fix, but both violate core project management principles and are not valid feasibility assessment actions.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Evaluate schedule compression techniques such as crashing or fast-tracking.

Schedule compression techniques like crashing (adding resources) or fast-tracking (performing tasks in parallel) are standard methods to shorten a project's duration without changing scope. The project manager should evaluate these to determine if the one-month acceleration is technically feasible given the project's constraints.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Evaluate schedule compression techniques such as crashing or fast-tracking.

    Why this is correct

    These techniques can shorten the schedule without changing scope.

  • Analyze the critical path to identify activities that can be compressed.

    Why this is correct

    Critical path analysis shows which activities affect project duration.

  • Increase the project scope to justify the shorter timeline.

    Why it's wrong here

    Increasing scope would extend the schedule, not shorten it.

  • Assess resource availability and the possibility of adding more resources.

    Why this is correct

    Additional resources may enable crashing.

  • Reduce the quality standards to speed up work.

    Why it's wrong here

    Reducing quality is not acceptable and may cause rework.

About these practice questions

One of 980 original PK0-005 practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.