Which agile artifact contains the prioritized list of all desired work for a product?

⚠ Common exam trap

Test-takers frequently confuse the product backlog (all prioritized work) with the sprint backlog (the subset selected for one sprint), since both are called 'backlogs' and candidates often pick the sprint backlog by reflex.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Product backlog

The product backlog is the single, prioritized list of all desired work for a product, owned and continuously refined by the Product Owner. It contains features, enhancements, bug fixes, and technical work ordered by business value, and it serves as the master source from which sprint backlogs are drawn. Because it is prioritized and comprehensive, it matches the question's definition exactly.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Burndown chart

    Why it's wrong here

    A burndown chart plots remaining work against time to track sprint progress; it holds no prioritised backlog. It is tempting because it visualises outstanding work, but the product backlog is the artefact that actually lists and orders all desired work.

  • ✗

    Sprint backlog

    Why it's wrong here

    The sprint backlog holds only the items selected for the current sprint, not the full prioritised product list. It tempts because it is the team's active work list, and would be correct when asking what work the team committed to during this iteration.

  • ✗

    Definition of done

    Why it's wrong here

    The definition of done is a shared quality checklist for completed increments, containing no prioritised work items. It tempts because it governs whether backlog items count as finished, and would be correct when asking what criteria an increment must satisfy.

  • ✓

    Product backlog

    Why this is correct

    The product backlog is the single, ordered list of every desired feature, fix, and enhancement for the product, with the highest-value items prioritised first. This directly satisfies the stem's requirement for a prioritised list of all desired work, distinguishing it from the sprint backlog, which holds only the subset selected for one iteration.

About these practice questions

This PK0-005 question is part of Courseiva's 954-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official CompTIA exam blueprint

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.