Which agile artifact contains the prioritized list of all desired work for a product?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Product backlog
The product backlog is a prioritized list of all features, enhancements, and fixes needed for the product.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Burndown chart
Why it's wrong here
Burndown charts show remaining work, not a list of work.
- ✗
Sprint backlog
Why it's wrong here
The sprint backlog contains only work committed for a specific sprint.
- ✗
Definition of done
Why it's wrong here
DoD defines quality criteria, not a list of work.
- ✓
Product backlog
Why this is correct
Correct: The product backlog is the single source of requirements for any changes to the product.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.