Courseiva
Project Management ConceptsmediumMultiple ChoiceObjective-mapped

PK0-005 Project Management Concepts Practice Question

A project manager is evaluating two project proposals. Proposal A has an NPV of $50,000 and a payback period of 2 years. Proposal B has an NPV of $30,000 and a payback period of 1.5 years. Which proposal is more financially beneficial based on NPV?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Proposal A because it has a higher NPV

Net Present Value (NPV) is the sum of present values of future cash flows. A higher NPV indicates greater profitability. Payback period is secondary.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Proposal B because it has a shorter payback period

    Why it's wrong here

    NPV is a more comprehensive measure of profitability than payback period.

  • Cannot be determined from the information given

    Why it's wrong here

    NPV directly compares profitability.

  • Both are equally beneficial

    Why it's wrong here

    The NPVs are different; higher NPV is better.

  • Proposal A because it has a higher NPV

    Why this is correct

    Correct. Higher NPV means more profitability.

About these practice questions

This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.