PK0-005 Project Management Concepts Practice Question
Which project life cycle phase involves obtaining formal acceptance of the project deliverables?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Closing
The closing phase includes finalizing all activities, obtaining stakeholder acceptance, and closing the project.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Planning
Why it's wrong here
Planning develops the project management plan.
- ✓
Closing
Why this is correct
Closing obtains formal acceptance and closes the project.
- ✗
Executing
Why it's wrong here
Executing completes the work defined in the plan.
- ✗
Initiating
Why it's wrong here
Initiating defines the project and authorizes it.
Go deeper
Related to this question
About these practice questions
This PK0-005 question is part of Courseiva's 980-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This PK0-005 practice question is part of Courseiva's free CompTIA certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the PK0-005 exam.