Courseiva

CAPM · domain

scenario questions

Practise Certified Associate in Project Management CAPM scenario questions practice questions — original exam-style scenarios with answer choices, explanations, and analysis of common mistakes.

451 questions126 easy188 medium137 hard

Focused practice

Practice scenario questions questions

Scored sessions drawing only from this domain — pick a length below.

Start 20-question practice test →

What this domain covers

What to know about scenario questions

scenario questions questions test whether you can apply the concept in context, not just recognise a definition.

How the topic appears in realistic exam-style scenarios.

Which detail in the question changes the correct answer.

How to eliminate plausible but wrong options.

How to connect the question back to the wider exam objective.

Watch out for

Common scenario questions exam traps

  • ▸Answering from memory before reading the full scenario.
  • ▸Missing a constraint such as cost, availability, security, scope or command context.
  • ▸Choosing a broad answer when the question asks for the most specific fix.
  • ▸Ignoring why the wrong options are tempting.

Question index

All scenario questions questions (451)

Click any question to see the full explanation, or start a practice session above.

1

Which THREE of the following are considered key schedule management tools for predictive projects?

Medium
2

A project team is developing a quality management plan for a predictive software development project. Which tool is most appropriate to identify the root causes of potential defects?

Easy
3

A project manager wants to ensure that all project documents are properly managed and approved. Which process group focuses on controlling changes to project documents?

Medium
4

You are a business analyst working on a project to digitize the supply chain operations of a large logistics company. After completing the requirements documentation, you review the requirements against the organization's strategic goals. You discover that several key requirements directly conflict with the company's recently announced strategic objective to reduce carbon emissions by 30% within two years. Specifically, the proposed solution relies on increased just-in-time deliveries that would require more transportation, contradicting the sustainability goal. You bring this to the attention of the project sponsor, who is the VP of Operations. The sponsor acknowledges the conflict but insists on proceeding with the original requirements, arguing that the strategic goal is not feasible and that operational efficiency is more important. The project is already approved and has a significant budget. What should the business analyst do?

Hard
5

A company transitioning from a waterfall to a Scrum framework wants to ensure continuous improvement. Which Scrum event is specifically designed for inspecting and adapting the process?

Easy
6

During project execution, a key stakeholder requests a change that would add a new feature. The project manager assesses the impact and finds that it will increase the project cost by 15% and extend the schedule by three weeks. The sponsor is concerned about the budget but sees the value. What should the project manager do next?

Hard
7

A business analyst is working on a project to replace a legacy customer relationship management (CRM) system. The project manager asks the BA to ensure that all requirements are aligned with the organization's strategic goals. Which of the following best describes the purpose of tracing requirements to business objectives?

Easy
8

During Sprint Planning, the Product Owner proposes a user story that is too large to fit in one Sprint. What should the team do?

Medium
9

Which THREE are principles of the Agile Manifesto? (Choose three.)

Hard
10

Which THREE of the following are outputs of the Control Quality process?

Hard
11

A project manager is creating a project scope statement for a predictive project. Which element is typically included in the project scope statement?

Medium
12

A Scrum Master is helping a team improve its use of the Definition of Done. The team currently has no shared Definition of Done, and each Developer applies their own quality standard. Which TWO actions best align with Scrum? (Choose two.)

Hard
13

A team using Kanban has a policy that limits work in progress at the 'In Progress' column to three items. Despite this, the team frequently exceeds the limit, and the board shows many items stuck in 'In Progress' while 'Testing' is empty. Which action best addresses the root cause?

Hard
14

During the planning phase of a predictive project, the project manager is estimating costs. Which cost estimation technique uses historical data from similar projects?

Easy
15

A Scrum team is midway through a two-week Sprint when the Product Owner introduces a new high-priority feature request from a key stakeholder. The team has already completed about 40% of the Sprint Backlog. According to Scrum, what should the team do?

Medium
16

A project manager is leading a project to implement a new customer relationship management (CRM) system. During a status meeting, a stakeholder suggests adding a feature that would allow integration with a social media platform. This feature was not in the original scope. What should the project manager do first?

Medium
17

A project manager is leading a project to develop a new mobile application. The project sponsor asks for a status update and wants to know the current project schedule performance. The project manager calculates that the Schedule Performance Index (SPI) is 0.85 and the Cost Performance Index (CPI) is 1.10. What is the most accurate interpretation of these metrics?

Medium
18

Which THREE are events in the Scrum framework? (Choose three)

Easy
19

A project manager is developing the project schedule for a software development project. The team has identified the activities and their dependencies. The project manager needs to determine the critical path. Which statement best describes the critical path?

Medium
20

Which of the following best describes a project versus ongoing operations?

Easy
21

Which document formally authorizes the project manager to use organizational resources to execute the project?

Easy
22

A business analyst is introducing a formal business analysis framework to an organization that has previously operated without one. The project manager asks why such a framework is needed. What is the primary benefit of using a business analysis framework?

Medium
23

Which THREE of the following are core values of the Agile Manifesto?

Hard
24

A project manager is developing the project schedule for a predictive building renovation project. The project manager needs to determine the early start and early finish dates for each activity. Which technique should the project manager use?

Medium
25

During a project, a stakeholder requests a change that adds new functionality. The BA determines the change is feasible but will delay the schedule. What should the BA do first?

Medium
26

In earned value management, if the Cost Performance Index (CPI) is 0.8 and the Schedule Performance Index (SPI) is 1.2, what does this indicate?

Hard
27

Which THREE of the following are techniques commonly used in business analysis frameworks to elicit requirements?

Hard
28

Which THREE of the following are tools and techniques used in the Control Schedule process?

Hard
29

A Scrum Team has been delivering increments every Sprint, but the Product Owner complains that the increments do not provide value to users. The Developers argue that they meet the Definition of Done. What should the Scrum Master do first?

Hard
30

A project manager has just been assigned to lead a project that is still in the initiation phase. The sponsor asks the project manager to create the document that formally authorizes the project and gives the project manager authority to apply organizational resources to project activities. Which document should the project manager create?

Easy
31

A Scrum team is halfway through a two-week Sprint when the Product Owner asks them to add a new high-priority feature that was not in the Sprint Backlog. The team believes they can complete it without jeopardizing the Sprint Goal. According to Scrum, what should the team do?

Medium
32

A project manager is leading a software upgrade project. The project sponsor wants to know the total duration required if all activities start as early as possible and no resource constraints exist. Which technique should the project manager use to determine this?

Hard
33

In a predictive (waterfall) project, the project phases are completed sequentially. If the design phase is delayed by two weeks, what is the likely impact on the project?

Medium
34

A project manager is reviewing the project schedule and sees that Task D depends on the completion of Task C, but Task C can start only after Task B finishes. Task B can start only after Task A. This is an example of which dependency?

Medium
35

A project manager is developing the project charter for a new marketing campaign. The sponsor asks for a high-level document that formally authorizes the project and gives the project manager authority to apply organizational resources. Which of the following best describes the purpose of the project charter?

Easy
36

Which THREE elements are typically included in a project business case?

Hard
37

A distributed Scrum team is having difficulty with communication across time zones. The Daily Scrum is scheduled at 9 AM in the US, which is midnight in India. What is the best approach to resolve this?

Hard
38

A project manager is preparing to close a completed internal software project. Before final closure, the sponsor asks which activities must be performed as part of the Close Project or Phase process. (Choose two.)

Hard
39

In a hybrid agile project, the team uses Scrum for development but the organization requires a detailed upfront plan. How can the team comply while staying agile?

Medium
40

Which THREE principles are common to multiple agile methodologies?

Hard
41

A project is behind schedule. Which schedule compression technique involves adding additional resources to critical path activities?

Medium
42

A project manager is performing qualitative risk analysis. Which TWO of the following are typical outputs of this process? (Select TWO)

Medium
43

During project planning, the team identifies that the project requires a specific vendor for a critical component. Which process group is being executed?

Easy
44

A BA is conducting stakeholder analysis and needs to categorize stakeholders based on their influence and interest. Which grid is commonly used?

Medium
45

A project manager is estimating the duration of an activity. The optimistic estimate is 4 days, the pessimistic is 12 days, and the most likely is 6 days. Using the PERT three-point estimate, what is the expected duration?

Easy
46

A team is working on a project with high uncertainty. Which agile framework is most suitable?

Medium
47

A Kanban team notices that cycle time is increasing despite stable demand. Which action is most likely to reduce cycle time?

Hard
48

A Scrum Team is preparing for its Sprint Retrospective. The Scrum Master wants to ensure the event is effective. Which two actions should the Scrum Master take to support a productive retrospective? (Choose two.)

Medium
49

A project manager is assigned to a project in a matrix organization. Who typically has authority over resource assignment and prioritization?

Easy
50

In Kanban, what is the primary purpose of limiting Work in Progress (WIP)?

Easy
51

Which THREE are common project constraints that must be balanced?

Hard
52

Which of the following is a characteristic of the project life cycle?

Easy
53

What is the main advantage of a projectized organization structure?

Hard
54

A project manager is evaluating the impact of a potential risk on project objectives. The risk has a probability of 0.3 and an impact of $50,000. What is the expected monetary value (EMV) of this risk?

Hard
55

A project manager is leading a website redesign under a functional organizational structure. The team members report to their functional managers and are assigned to the project only part-time. The project manager needs a designer to work extra hours to meet a milestone but does not control the designer's workload. What is the most appropriate action?

Medium
56

Which THREE of the following are components of the project management plan?

Medium
57

Which of the following is a key benefit of using a Kanban board?

Easy
58

A mid-sized insurance company is implementing a new claims management system using a traditional waterfall approach. The business analyst (BA) spent three months gathering and documenting detailed requirements, which were signed off by stakeholders. However, during the development phase, the claims processing team requests frequent changes due to evolving regulatory requirements and customer feedback. The project manager is concerned about scope creep and budget overruns. The development team is frustrated because rework is affecting their velocity. The BA needs to recommend an approach that balances flexibility with control. The organization has limited experience with agile methods but is open to change. The BA should recommend:

Hard
59

A business analyst is using a requirements traceability matrix. A test case failure reveals that requirement REQ-007 was not implemented correctly. What does the RTM help the BA identify?

Hard
60

A project manager is leading a predictive project to implement a new enterprise resource planning (ERP) system. During the Plan Quality Management process, the project manager is identifying quality requirements and documenting how the project will demonstrate compliance. Which two of the following are inputs to this process? (Choose two.)

Hard
61

A project team is identifying the business need for a new system. Which business analysis activity should be performed first?

Easy
62

A business analyst is creating a model to represent the flow of data between external entities and the system. The goal is to show the inputs, outputs, and storage of data without focusing on the internal processing logic. Which business analysis technique should the BA use?

Easy
63

An organization is scaling Scrum across multiple teams. They have dependencies between teams that cause delays. What is the most appropriate framework to address this?

Hard
64

Which document formally authorizes the project and provides the project manager with authority to apply organizational resources?

Easy
65

During the initiation phase of a project, the project manager needs to identify stakeholders. What is the primary purpose of stakeholder identification at this stage?

Easy
66

A project manager is initiating a project to develop a new mobile application. The business environment is highly uncertain, and requirements are expected to evolve frequently. Which business analysis framework is most appropriate for this scenario?

Medium
67

In Extreme Programming (XP), which practice involves a customer representative working closely with the team to define and prioritize features, providing continuous feedback throughout the project?

Easy
68

Which THREE of the following are characteristics of a matrix organizational structure that impact project management?

Hard
69

A business analyst is facilitating a requirements workshop for a new customer relationship management (CRM) system. Several stakeholders from sales, marketing, and customer support are present. The BA wants to generate a large number of ideas quickly, encourage creativity, and avoid early criticism. Which technique is most appropriate?

Medium
70

Refer to the exhibit. A project administrator applies an organizational policy that requires a project charter signed by the sponsor and the functional manager before project work can commence. A project manager has not yet obtained these signatures. What is the effect on the project team's ability to start work?

Medium
71

A team using Scrum consistently fails to complete all planned work in a sprint. What should the Scrum Master do first?

Medium
72

You are a business analyst for a large retail company implementing a new inventory management system. The project uses a waterfall business analysis framework. During the requirements phase, you have completed stakeholder analysis, conducted interviews, and documented functional requirements. Now, during requirements validation, the warehouse manager (a key stakeholder) states that the system must support real-time inventory updates from handheld scanners, a requirement not previously mentioned. The project manager is concerned because this requirement could impact the budget and schedule, and the design phase is scheduled to begin next week. You have a requirements prioritization meeting tomorrow. The warehouse manager insists this is critical for operations. The project sponsor expects all requirements to be finalized before design. What is the best course of action?

Hard
73

A project manager is leading a predictive project to build a bridge. The project is in the execution phase, and the team has completed 40% of the work. The project manager wants to forecast the final project cost using earned value management. Which formula should be used to calculate the estimate at completion (EAC) when the current cost performance is expected to continue?

Medium
74

Drag and drop the steps for creating a work breakdown structure (WBS) in the correct order.

Medium
75

A project manager is managing a complex IT project with many inter-dependencies. During execution, a key stakeholder requests a feature that will require rework of several completed deliverables. The project manager wants to minimize disruption to the project. What is the best course of action?

Hard
76

A project manager is developing the project management plan for a hospital wing expansion using a predictive approach. The sponsor wants a single document that will authorize the project manager to assign organizational resources to project activities. Which document should the project manager reference?

Medium
77

A business analyst has developed a working prototype for a new user interface. The prototype is used to demonstrate the workflow to stakeholders and gather feedback. Which type of requirements validation does this represent?

Hard
78

A business analyst is developing a business case for a proposed IT system. Which component should be included to evaluate the financial viability?

Medium
79

Refer to the exhibit. What issue does the Kanban board reveal?

Easy
80

Which document serves as the primary source for defining the product scope?

Easy
81

A Scrum Team is halfway through a two-week Sprint when the Product Owner learns that a competitor has released a similar feature. The Product Owner wants to add several new Product Backlog items to the current Sprint to respond quickly. What should the Scrum Master do?

Hard
82

A project team is evaluating a proposed solution that reduces operating costs by $200,000 annually but requires an initial investment of $800,000. The project lifespan is 5 years and the discount rate is 8%. What is the net present value (NPV) of this solution? (Assume annual cost savings occur at year-end.)

Hard
83

A project manager is estimating the duration of a task using parametric estimation. Historical data shows that a similar task took 10 hours per unit, and 50 units are required. The team's productivity is expected to be 20% slower due to new team members. What is the estimated duration?

Hard
84

In a predictive project, the project manager wants to ensure that the project team understands their roles and responsibilities. Which document is used to define roles and responsibilities?

Medium
85

Which THREE of the following are typically included in a project management plan (as opposed to project documents)?

Easy
86

Which TWO of the following are outputs of the Define Activities process? (Select exactly 2.)

Medium
87

According to the Scrum Guide, which THREE of the following are Scrum events?

Hard
88

A project manager is performing risk identification. Which two inputs are essential for this process? (Choose two)

Hard
89

A medium-sized software company is developing a new mobile application. The project manager, Alex, has a team of 10 developers and 2 testers. The organization uses a hybrid approach combining waterfall planning for the overall phases and agile for individual iterations. In the first iteration, the team committed to completing 20 user stories. During the sprint, two developers left the company, and the remaining team members had to pick up their tasks. The product owner is concerned about the delivery date. Alex needs to communicate the impact to stakeholders. What should Alex do first?

Hard
90

A BA is analyzing the cost-benefit analysis for a project and finds that the net present value (NPV) is negative. What does this indicate?

Hard
91

A software development team has been using a feature branch workflow with long-lived branches. They frequently experience merge conflicts and integration delays. The team wants to adopt a more agile approach to reduce these issues. Which practice should the team adopt?

Medium
92

Which TWO of the following are commonly used techniques for requirements prioritization?

Easy
93

Which THREE of the following are commonly used techniques for requirements elicitation?

Hard
94

Which TWO practices are characteristic of Extreme Programming (XP)? (Choose two)

Medium
95

A business analyst is working on a project to replace a legacy billing system. The project sponsor wants to ensure that the new system meets the needs of the finance department. Which technique should the business analyst use to understand the detailed steps and decision points in the current billing process?

Medium
96

Which THREE roles are defined in the Scrum Guide? (Select THREE)

Hard
97

A project manager is closing a phase in a predictive life cycle. Which document should be updated to record lessons learned for future phases?

Hard
98

Which TWO of the following are outputs of the Define Activities process?

Medium
99

During a project review, the project manager is asked to explain the difference between project management and operations management. Which statement accurately describes this difference?

Easy
100

A project manager is reviewing the project schedule and notices that a task has a lead time of 2 days. What does this indicate?

Medium
101

During the requirements elicitation for a new software system, the business analyst (BA) conducts a series of interviews with stakeholders. After the first interview, the BA realizes that the questions are too technical and the stakeholders are struggling to provide clear requirements. What should the BA do to improve the elicitation process?

Medium
102

Which document formally authorizes the project and provides the project manager with the authority to apply organizational resources to project activities?

Easy
103

Which TWO of the following are outputs of the Identify Risks process?

Hard
104

A business analyst is creating a requirements traceability matrix (RTM) for a project. Which of the following is the primary purpose of an RTM?

Easy
105

A business analyst is creating a model to represent the flow of data between external entities, processes, and data stores for a new payroll system. The BA needs to show how data moves through the system and what transformations occur. Which model is most suitable?

Easy
106

A startup is using Scrum to develop a mobile app. The product owner has a clear vision and has written detailed user stories for the first release. During sprint planning, the development team estimates that they can complete 40 story points per sprint. However, after two sprints, the team has only completed 30 points per sprint. The product owner is concerned and wants to hold the team accountable. The team says that the estimates were optimistic and that they are still learning the technology. The Scrum Master notices that the team is not using pair programming or test-driven development (TDD) as originally planned. The product owner suggests reducing scope for the next sprint to match the team’s actual velocity. The Scrum Master must decide the best way to proceed. What should the Scrum Master do?

Medium
107

A business analyst needs to gather input from a large number of geographically dispersed stakeholders about their preferences for a new system. The project has a limited budget and timeline. Which elicitation technique is most efficient in this scenario?

Easy
108

A project manager is leading a software development project using an agile approach. The team has completed several sprints, and the product owner wants to add a new feature that was not in the original release plan. The project manager needs to determine how this change should be handled. Which of the following is the most appropriate action?

Hard
109

Which TWO of the following are generally true about projects versus operations? (Choose two)

Easy
110

A business analyst is conducting a stakeholder analysis and discovers that a key stakeholder has high power but low interest in the project. According to the Power/Interest Grid, what is the recommended engagement strategy for this stakeholder?

Medium
111

A business analyst is facilitating a workshop to define the scope of a new customer relationship management (CRM) system. The project manager insists on including a feature that automates email campaigns, but the BA has identified that this feature is outside the agreed budget and timeline. The product owner supports the feature because it was requested by a key customer. What should the BA do first?

Hard
112

In an Agile framework, when should the business analyst perform backlog refinement?

Easy
113

During a project, the team identifies a risk that could cause a 20% increase in cost. The project manager decides to accept the risk because the probability is low. What risk response strategy is being used?

Hard
114

A project manager in a weak matrix organization is having difficulty getting team members to complete project tasks because they prioritize their functional work. Which type of power should the project manager primarily rely on to influence the team?

Hard
115

Which THREE of the following are tools and techniques used in the Control Schedule process? (Select exactly 3.)

Hard
116

Based on the exhibit, which requirement is not yet linked to a test case?

Medium
117

A business analyst is preparing for a requirements review meeting with stakeholders from various departments. The BA wants to ensure the review is effective and that the requirements are validated. Which two actions should the BA take to prepare for the review? (Choose two.)

Hard
118

A project manager is performing quality control on a batch of manufactured components. The team collects data on the number of defects per unit and wants to determine whether the process is stable over time and to identify any unusual patterns. Which tool should the project manager use?

Hard
119

An XP team is practicing pair programming. A new developer feels uncomfortable because the partner frequently corrects their code. What is the best way to foster a positive pairing experience?

Medium
120

A project manager is leading a software development project. The business analyst has identified that the current requirements gathering process does not align with the enterprise's business analysis framework. The team is experiencing frequent scope changes and rework. What should the project manager do first to address this issue?

Medium
121

In a predictive project life cycle, which three of the following are characteristics of a work breakdown structure (WBS)? (Choose three)

Medium
122

Drag and drop the steps for performing risk management planning in the correct order.

Medium
123

A project manager is creating a risk response plan for a predictive construction project. One risk has a high probability and high impact. The team decides to purchase insurance to cover potential losses. Which risk response strategy is being used?

Hard
124

A Scrum team's Sprint Retrospective keeps producing the same three improvement actions every Sprint, and none of them get implemented. The Scrum Master wants the team to actually finish improvements. Which approach best fits Scrum practice?

Medium
125

Which THREE of the following are characteristics of a project?

Medium
126

A business analyst is assessing the feasibility of a proposed new online ordering system for a restaurant chain. The BA needs to evaluate whether the system can be developed with the available technology and skills within the organization. Which type of feasibility is the BA primarily assessing?

Medium
127

A business analyst is evaluating whether a proposed project aligns with the organization’s strategic goals. Which framework is best suited for this purpose?

Medium
128

A project manager is using a predictive approach to manage project costs. Which THREE of the following are cost estimation techniques? (Select THREE)

Medium
129

A product owner is writing user stories for a new feature. Which of the following is a best practice for ensuring the stories are well-formed?

Easy
130

A project manager is planning a regulatory compliance upgrade for a hospital's records system. The sponsor wants success measured in a way that can be independently verified after closure. Which action best aligns with establishing objective, measurable project success criteria?

Hard
131

A project has a cost baseline of $100,000. At the end of month 2, the planned value is $30,000, and the actual cost is $40,000. If the earned value is $25,000, what is the cost variance?

Easy
132

Drag and drop the steps for managing project quality in the correct order.

Medium
133

In a requirements prioritization session, the team uses MoSCoW. A feature that is important but not critical, and could be postponed without major impact, should be classified as:

Medium
134

You are the project manager for a construction project using a predictive plan-based methodology. The project has a detailed scope baseline approved by stakeholders. During the execution phase, a key stakeholder requests an additional feature that would require significant changes to the scope. You estimate the impact will increase the project cost by 15% and extend the schedule by three weeks. The project charter clearly defines the original scope and budget. What is the BEST course of action?

Easy
135

You are the business analyst for a project developing a mobile banking application. The project is in the requirements elicitation phase. One of the key stakeholders, the head of security, is on an extended leave and will not be available for three weeks. The project timeline is aggressive, and the project manager insists on completing requirements gathering within two weeks to stay on schedule. You have held initial interviews with other stakeholders, but the security requirements are critical because the app will handle sensitive financial data. The quality assurance lead suggests using a survey to collect security requirements from the security team, but the security team members are reluctant to provide input without their manager's approval. What should you do?

Medium
136

Which THREE of the following are processes that belong to the Planning process group?

Hard
137

A project manager is planning risk responses for a high-impact, low-probability risk. The team decides to purchase an insurance policy to cover potential losses. Which risk response strategy is being used?

Hard
138

You are managing a predictive project to build a new office building. The project is in the execution phase. During a weekly progress meeting, the electrical contractor reports that a critical piece of switchgear has a 6-week lead time, but it was not ordered because the team assumed it would be procured later. The project schedule shows the switchgear installation activity is supposed to start in 4 weeks. The project manager reviews the procurement management plan and realizes the procurement process was not followed. The project has a tight deadline and cannot accommodate a 6-week delay. What is the best course of action for the project manager?

Medium
139

Which TWO are Scrum artifacts? (Choose two.)

Easy
140

A construction project manager, Maria, is overseeing the building of a bridge. The project has a fixed budget and schedule. During the execution phase, the quality audit reveals that the concrete used does not meet the specified strength requirements. The concrete supplier insists that the concrete meets industry standards. However, the project specifications require a higher strength grade. Maria must decide on corrective action. What should she do?

Hard
141

Which TWO of the following are examples of project constraints? (Choose two.)

Medium
142

A business analyst is defining the requirements for a new online banking feature that allows customers to transfer funds between accounts. The security team insists that the feature must comply with multi-factor authentication (MFA) regulations. The marketing team wants to minimize steps to improve user experience. Which type of requirement best describes the MFA compliance mandate?

Hard
143

A project manager is working on a research project where the scope is not clearly defined and requirements are expected to evolve. The sponsor wants to deliver value quickly and adapt to changes. Which project management approach is most appropriate?

Hard
144

A business analyst is defining the solution scope for a project to automate a manual approval process. The project sponsor wants to ensure that the solution will meet the business need without including unnecessary features. Which technique should the BA use to clearly define what is in and out of scope for the solution?

Hard
145

A project manager notices that the project is behind schedule. Which of the following actions is most appropriate to bring the project back on track?

Medium
146

A project manager is leading a construction project to build a community center. The project charter has been approved. The sponsor asks the project manager to begin detailed scheduling and to assign resources to specific tasks. According to the PMBOK Guide, which process group is the project manager currently entering?

Medium
147

A business analyst is facilitating a requirements workshop for a new customer relationship management (CRM) system. Participants include sales representatives, customer service managers, and IT support staff. The BA needs to ensure that all perspectives are captured and that the group reaches a shared understanding of the requirements. Which technique is most appropriate for this purpose?

Medium
148

A business analyst is evaluating the performance of a business analysis framework after project completion. Which metric best indicates the effectiveness of the requirements management process?

Hard
149

A business analyst is using a requirements management tool to store and track requirements. During a review, the BA notices that two stakeholders have conflicting requirements for the same system feature. What is the best approach to resolve this conflict?

Hard
150

A project manager is leading a project to develop a mobile application. The project sponsor asks the project manager to identify the key stakeholders and document their interests, involvement, and impact on project success. Which document should the project manager create?

Easy
151

A project team is struggling with unclear roles and responsibilities, leading to duplicated work and missed tasks. Which document should the project manager create or update to resolve this issue?

Easy
152

During a sprint review, the team demonstrates a new feature to stakeholders. One stakeholder says, 'This isn't what we wanted. We need a completely different approach.' The product owner is upset because the feature took two weeks to build. The team is frustrated because they followed the product owner's specifications exactly. The Scrum Master observes that the product owner did not involve stakeholders during the sprint and based the user stories on assumptions. The product owner wants to add the rework to the next sprint. However, the team's capacity is already full. The Scrum Master needs to help the team and product owner recover. What should the Scrum Master do first?

Medium
153

A Kanban team notices that their cumulative flow diagram (CFD) shows a widening band for the 'In Progress' column over several weeks, while the 'Done' band remains relatively flat. What is the most likely interpretation of this pattern?

Hard
154

During requirements elicitation, a stakeholder suggests a feature that is out of scope and would significantly increase project cost. What is the best action for the business analyst?

Medium
155

A project manager is using a predictive approach to manage a project. During the execution phase, the team is working on deliverables. Which process group involves tracking, reviewing, and regulating progress against the plan?

Easy
156

In Scrum, what is the purpose of the Sprint Retrospective?

Easy
157

Which THREE of the following are typical components of a business case?

Medium
158

A project manager is leading a team in a matrix organization where team members report to both a functional manager and the project manager. The project is in the planning phase. What is the primary responsibility of the project manager during this phase?

Easy
159

During project execution, a key stakeholder requests a change that would add a new feature to the product. The project manager evaluates the impact on scope, schedule, and cost. According to the change management plan, which step should the project manager take first?

Medium
160

A construction project is underway. The project manager receives a report that the concrete supplier will deliver late, causing a two-week delay. The project has no schedule reserve. What is the best course of action?

Medium
161

A business analyst is preparing a business case for a project with intangible benefits. How should the intangible benefits be presented to support the business case?

Hard
162

Drag and drop the steps for managing project communications in the correct order.

Medium
163

During project execution, a key stakeholder requests a new feature that was not included in the approved scope. What should the project manager do first?

Easy
164

An organization is transitioning from a traditional project management approach to Scrum. The project manager has been reassigned as a Scrum Master but continues to assign tasks to team members and track individual progress. The team is becoming demotivated. What should the Scrum Master do differently?

Medium
165

A project manager is developing the project charter for a new marketing campaign. The sponsor asks which document formally authorizes the project and gives the project manager authority to apply organizational resources. What is the correct answer?

Medium
166

A Scrum Team is preparing for its first Sprint. The Product Owner has a prioritized Product Backlog, and the team is defining its Definition of Done. Which two characteristics are essential for a useful Definition of Done? (Choose two.)

Medium
167

A project manager is leading a predictive project to develop a new software system. The project sponsor asks for a document that formally authorizes the project and provides the project manager with the authority to apply organizational resources to project activities. Which document should the project manager reference?

Easy
168

A project manager is leading a marketing campaign project for a regional retailer. The sponsor asks the project manager to classify the effort. The work involves producing a one-time series of promotional videos and launching them by a fixed holiday deadline, after which the team is released. Which characteristic best supports classifying this as a project rather than ongoing operations?

Medium
169

A business analyst is facilitating a requirements workshop. Which technique is best for generating a large number of ideas in a short time?

Easy
170

A Scrum Team is struggling with its Daily Scrum. Team members give detailed status updates to the Scrum Master, and the meeting often runs 30 minutes. The Scrum Master wants to improve the event. Which action best aligns with Scrum?

Medium
171

In business analysis, what is the purpose of a stakeholder analysis?

Easy
172

A project manager is leading a software development project. The sponsor has requested a new feature that was not part of the original scope. The project manager assesses that adding this feature will require additional resources and will extend the timeline by two weeks. What should the project manager do first?

Medium
173

Which TWO are benefits of creating a Work Breakdown Structure (WBS)?

Medium
174

A business analyst is evaluating the success of a recently completed project. The project delivered all requirements on time and within budget, but end-users are dissatisfied with the functionality. Which business analysis technique should the analyst use to assess this discrepancy?

Medium
175

A project manager is developing the project management plan for a complex software development project. The project manager needs to ensure that the plan includes all necessary subsidiary plans and baselines. Which three of the following are components of the project management plan? (Choose three.)

Hard
176

During a predictive project, a team member reports that a critical path activity is behind schedule by two days. To recover the schedule, the project manager should first:

Medium
177

A business analyst is creating a requirements traceability matrix. Which purpose does this serve?

Medium
178

A BA is conducting a feasibility study. Which factor is assessed to determine if the project aligns with strategic goals?

Easy
179

A project manager is leading a software development project using a predictive life cycle. The team has completed the requirements documentation and is now breaking down the work into smaller, manageable components. The project manager wants to ensure that the work is decomposed to the level where it can be reliably estimated and controlled. Which technique should the project manager use?

Medium
180

A Scrum team's Sprint Review is scheduled for Friday afternoon. The team has completed all but two Product Backlog items. The Product Owner asks the Scrum Master whether the incomplete items should be demonstrated during the Sprint Review. What is the most appropriate guidance the Scrum Master should provide?

Medium
181

A geographically distributed agile team using Scrum is experiencing frequent integration issues and delays caused by incompatible code changes. Which Extreme Programming (XP) practice would best address this problem?

Hard
182

Which TWO are benefits of using an iterative approach in agile projects?

Easy
183

You are a project manager in a functional organization managing a software upgrade project. The functional managers control resources and priorities. Your project requires a senior developer from the IT department for two weeks starting next Monday. The IT functional manager informs you that the developer is assigned to an urgent operational issue and cannot be released until further notice. The project has a fixed deadline in four weeks, and any delay will impact the next phase. You have already used your influence and escalated to senior management, but the functional manager insists on keeping the developer. What should you do next?

Medium
184

You are a business analyst on a project to replace the legacy inventory system with a cloud-based solution. The project is using a predictive lifecycle, and the requirements specification has been baselined. During the design phase, the vendor informs you that a key feature (real-time reporting) cannot be implemented within the current budget because it requires additional licensing. The feature is critical to the business case's expected cost savings. The project manager wants to descope the feature to stay within budget. As the business analyst, what is the most appropriate action?

Hard
185

A project team encounters this error during deployment. Which project document should be updated first?

Easy
186

A government IT project is being managed using a predictive lifecycle. The project must comply with numerous regulatory standards, including data privacy and security. The project manager developed a comprehensive quality management plan that includes regular quality audits by an independent team. At the first milestone quality audit, the auditor identifies three non-conformances related to documentation and testing procedures. The project manager is under pressure from the sponsor to stay on schedule. The project manager needs to address the non-conformances effectively while minimizing schedule impact.

Medium
187

A business analyst is working on a project to develop a new inventory management system. The project sponsor wants to ensure that all requirements are testable and verifiable. Which characteristic of effective requirements is most directly supported by writing requirements in a structured, consistent format with clear acceptance criteria?

Medium
188

A business analyst is defining the scope of a project to develop a new employee onboarding system. The project sponsor asks for a high-level view of the solution's features and their relationships. Which business analysis technique should the business analyst use to provide this view?

Easy
189

A project manager is developing the WBS for a large construction project. She has identified the major deliverables and decomposed them into work packages. Which of the following BEST describes the next step in the WBS creation process?

Medium
190

At the daily stand-up meeting, a team member consistently arrives 10 minutes late, causing the meeting to start late. What is the best agile practice to address this?

Easy
191

A project is being executed in a highly regulated industry. The quality management plan requires extensive documentation. During a quality audit, the auditor finds that some test results are missing. What is the MOST appropriate action for the project manager?

Hard
192

During requirements elicitation, a business analyst (BA) observes that key stakeholders are reluctant to share information due to a previous project's failure. The BA needs to build trust. Which technique should the BA use to encourage open communication?

Hard
193

A project manager is determining the sequence of activities for a construction project. Which tool is best suited for this purpose?

Easy
194

You are a business analyst on a project to replace a legacy claims processing system. Executive management wants to understand the expected benefits and costs before authorizing the project. Which document should you prepare to present the justification for the investment?

Medium
195

A project manager is assigned to a project that is in the planning phase. The sponsor asks the project manager to include a 10% contingency reserve in the budget. The project manager knows that the project has a high degree of uncertainty. What should the project manager do?

Hard
196

A project manager is developing a work breakdown structure (WBS) for a software development project. The team is struggling with defining the lowest-level work packages. Which technique should the project manager use to ensure the WBS is complete and properly decomposed?

Medium
197

A business analyst has completed elicitation for a customer portal project and now has a long list of raw stakeholder statements. Before the statements can be used as requirements, the analyst must distinguish which are true requirements. Which characteristic must a well-formed requirement exhibit?

Easy
198

After a change request is approved, a business analyst must update the requirements documentation. What is the most important step to ensure traceability?

Medium
199

A key stakeholder requests a new feature after the project requirements have been formally approved and the scope baseline has been set. What is the first process the project manager should follow?

Easy
200

In a predictive project, the project manager needs to estimate the cost of each work package with a high level of accuracy. Which technique is most appropriate?

Easy
201

Which of the following is NOT a purpose of the project charter?

Easy
202

A project team is working on a software development project. The project manager notices that the team is spending too much time on unplanned work, resulting in delays to the critical path. What technique should the project manager use to reduce unplanned work and improve focus?

Medium
203

A Scrum Team is struggling with unclear requirements. The Product Owner wants to ensure the team has a shared understanding of a user story before development begins. Which of the following is the most appropriate technique?

Easy
204

A project manager is executing a predictive project with a cost baseline of $500,000. At the end of the third month, the project has completed 40% of the work, and the actual cost incurred is $220,000. The project manager needs to forecast the total cost at completion. Which earned value management (EVM) estimate should the project manager use if the current cost performance is expected to continue?

Hard
205

Which TWO are outputs of the Initiating process group?

Medium
206

You are a business analyst on a project to develop a new online banking portal. The project is using a hybrid approach with both predictive and adaptive elements. The requirements have been documented in a functional specification, but during development, the product owner requests significant changes based on user feedback. The change control board (CCB) is slow to approve changes, causing delays. The project manager wants to minimize rework while still incorporating valuable feedback. As the business analyst, what is the best course of action?

Easy
207

An agile team is using a burndown chart for the first time. After six days of a two-week sprint, the burndown chart shows that the remaining work has increased compared to the previous day. The team is confused. They had completed several tasks, but new tasks were added to the sprint backlog after the sprint started. The product owner says the additions were urgent and necessary. The development team is frustrated because they feel the sprint goal is at risk. The Scrum Master must address this situation. What should the Scrum Master do?

Easy
208

A project team is conducting cost estimation for a project that uses a predictive lifecycle. They have historical data from similar projects. Which estimation technique is MOST appropriate?

Medium
209

During the planning phase of a predictive project, the project manager notices that the project schedule does not include all required deliverables. What is the most appropriate action to address this gap?

Easy
210

A business analyst is assigned to a project that aims to streamline the supply chain process in a manufacturing company. The project has a tight deadline, and the project sponsor wants to use a proven framework to ensure efficiency. During the initial analysis, the analyst finds that the current process has many manual handoffs and inconsistent data formats. Several cross-functional teams have conflicting priorities. The sponsor asks for a recommendation that balances structure with flexibility. As the business analyst, which approach should you recommend?

Medium
211

A business analyst is performing a cost-benefit analysis for a proposed system upgrade. The upgrade costs $50,000 upfront and saves $15,000 per year in operational costs. The project has a 5-year horizon. What is the payback period in years?

Hard
212

During project execution, a stakeholder requests a new feature that was not in the original scope. The project manager determines that the feature can be accommodated without affecting the critical path, but will increase costs. According to the predictive plan-based methodology, what should the project manager do NEXT?

Hard
213

A business analyst needs to document the relationships between requirements, design, and test cases. Which artifact is best for this purpose?

Easy
214

During a requirements workshop, two key stakeholders disagree on a critical requirement. The project manager asks the business analyst to facilitate a resolution. Which approach is most effective?

Hard
215

During the project kickoff meeting, a key stakeholder expresses concerns about the project scope. What should the project manager do first?

Medium
216

During a Scrum sprint, the development team discovers that a critical dependency on another team's API cannot be resolved until the next sprint. The product owner insists on delivering the current sprint goal without adjusting scope. The team is struggling to meet the definition of done. What should the Scrum Master do first?

Hard
217

Refer to the exhibit. The team wants to pull a new item into In Progress. What should they do first?

Medium
218

A project is in the execution phase. The earned value analysis shows a Cost Performance Index (CPI) of 0.8 and a Schedule Performance Index (SPI) of 0.9. What is the best interpretation of these metrics?

Medium
219

In a predictive project, the project sponsor requests a scope change that will significantly increase the project cost. The project manager should FIRST:

Hard
220

An agile team is using Extreme Programming (XP). A developer wants to refactor a complex module but is concerned about breaking existing functionality. Which XP practice should the developer rely on to safely make changes?

Medium
221

A BA is prioritizing a large number of requirements. Which TWO techniques are best suited for this scenario?

Medium
222

A project manager has just been assigned to lead a new product launch. Before detailed planning can begin, the sponsor asks what formal document authorizes the project and gives the project manager authority to apply organizational resources. Which document should the project manager reference?

Easy
223

Which THREE of the following are components typically included in a business case?

Medium
224

A startup is adopting Scrum for the first time. During the Sprint Review, stakeholders request many changes to the product increment. What is the best way for the Scrum Master to handle this?

Easy
225

A business analyst is managing requirements for a software upgrade project. The project sponsor wants to ensure that every requirement can be traced back to a business need. What is the primary purpose of requirements traceability?

Medium
226

In a requirements gathering workshop, two stakeholders have differing opinions on the system interface design. The business analyst decides to use a technique that involves listing pros and cons of each option. Which technique is being used?

Hard
227

Drag and drop the steps for controlling project changes according to the integrated change control process.

Medium
228

A project manager is evaluating two project proposals. Proposal A has a benefit-cost ratio (BCR) of 1.2 and a payback period of 3 years. Proposal B has a BCR of 1.5 and a payback period of 4 years. The organization has limited funds and wants to maximize return on investment. Which proposal should the project manager recommend?

Medium
229

A milestone in a project schedule is best described as:

Easy
230

An agile team has been running two-week Sprints for several months. During each Sprint Review, stakeholders provide feedback, but the team notices that the same concerns keep resurfacing and no one owns follow-up actions. The Scrum Master wants to ensure that the team inspects how it is working and adapts its process. Which Scrum event should the Scrum Master focus on to address this?

Medium
231

During Sprint Planning, the Development Team realizes that the total effort for the selected Product Backlog items exceeds their historical velocity. What should the team do?

Medium
232

A business analyst is verifying that all requirements have corresponding test cases. They find a requirement that has no linked test case. What should the BA do first?

Hard
233

A project manager is planning a predictive project to upgrade a hospital's HVAC system. The project has a fixed budget and a strict regulatory deadline. The project manager needs to determine the total duration of the project by analyzing the sequence of activities and their dependencies. Which technique should the project manager use?

Medium
234

Which THREE items are typically included in a business analysis plan? (Choose three.)

Medium
235

Which TWO are benefits of self-organizing teams?

Easy
236

Which of the following is a key output of the Plan Risk Management process?

Medium
237

Which THREE of the following are key components of a project management plan for a predictive project?

Hard
238

A project manager is leading a project to implement a new customer relationship management (CRM) system. The project is in the execution phase. A key stakeholder requests a significant change to the system's functionality. The project manager assesses the change and determines that it will impact the project scope, schedule, and cost. What should the project manager do first?

Hard
239

What is the primary role of the Product Owner in Scrum?

Easy
240

A business analyst is tasked with modeling the logical data requirements for a new customer relationship management (CRM) system. Which artifact should the BA create to show the relationships between customer entities and their attributes?

Easy
241

A project team is working on a construction project. The project manager notices that the team is spending excessive time clarifying task responsibilities. Which project management artifact would most directly help assign clear ownership?

Easy
242

A project manager is leading a research project with a fixed budget and a tight deadline. The project team is distributed across three time zones. The project manager needs to ensure that all team members have access to the latest project documents and that changes are tracked. Which tool or technique would best support this requirement?

Hard
243

In which project management process group is the project charter developed?

Easy
244

A project manager is developing the project schedule for a software implementation project. The project manager needs to determine the early start and early finish dates for each activity, taking into account dependencies and resource constraints. Which technique should the project manager use?

Medium
245

A business analyst is gathering requirements for a new reporting system. The stakeholders are located in different time zones and have conflicting availability. Which elicitation technique would be most effective for this situation?

Medium
246

A construction project has a predefined budget and strict deadline. The project manager is using a work breakdown structure (WBS) to decompose deliverables. Which level of the WBS provides the basis for estimating and scheduling?

Easy
247

A business analyst is validating requirements and discovers that several requirements conflict with each other. The project sponsor insists on including all conflicting requirements to satisfy different stakeholders. What is the best course of action for the BA?

Hard
248

A project manager is leading a software development project. During a team meeting, a team member suggests adding a new feature that was not in the original scope. The project manager wants to evaluate the impact of this change on the project constraints. Which document should the project manager consult first to understand the baseline scope?

Medium
249

A project manager is developing the project schedule using a predictive approach. The project involves multiple dependencies and a critical path that has been identified. Which TWO of the following are valid techniques for schedule compression that can be applied to activities on the critical path?

Hard
250

A business analyst is facilitating a requirements elicitation session for a new customer relationship management system. Several stakeholders from sales, marketing, and customer support are present, but the discussion keeps drifting into unrelated operational complaints. Which facilitation technique should the business analyst use to keep the session focused on gathering requirements?

Medium
251

Which TWO of the following are benefits of using a project management plan? (Choose two)

Hard
252

During the creation of the project schedule, a project manager needs to identify and document the logical relationships among activities. Which technique should be used?

Medium
253

A project manager is developing the project charter for a new marketing campaign. The sponsor emphasizes that the project must be completed within six months and cannot exceed a budget of $200,000. Which of the following best describes these constraints?

Easy
254

A business analyst is using the MoSCoW technique to prioritize requirements. A feature is determined to be important but not critical for the first release. How should it be categorized?

Medium
255

A business analyst is using a context diagram to model the scope of a system. What does a context diagram primarily show?

Easy
256

A BA is conducting a needs assessment for a new system. Which activity is performed first?

Easy
257

A project manager is performing risk response planning for a high-priority risk. The risk has a high probability and high impact. Which response strategy is most appropriate to reduce the probability and/or impact?

Hard
258

A business analyst is eliciting requirements for a new online banking feature. The project sponsor wants to ensure that the requirements are aligned with the organization's strategic goals, such as increasing customer retention and reducing call center volume. Which technique should the BA use to trace requirements back to business goals?

Medium
259

Which TWO of the following are outputs of the Plan Stakeholder Engagement process?

Hard
260

A Scrum team is halfway through a two-week Sprint when the Product Owner asks the developers to add a new high-value feature immediately. The Sprint Goal is still achievable. What should the developers do?

Easy
261

During a sprint retrospective, the team identifies that they often spend too much time in daily stand-up meetings. What is the recommended timebox for the daily Scrum in Scrum?

Easy
262

A team adopting Kanban wants to visualize its workflow and identify bottlenecks. Which Kanban practice should the team implement first?

Easy
263

A Scrum Master notices that the development team is not self-organizing and often waits for instructions. What is the best coaching approach?

Medium
264

Which TWO of the following are outputs of the 'Define Activities' process in predictive project management?

Medium
265

A business analyst creates a document that maps each requirement to its source and to the test case that will verify it. This document is called:

Easy
266

A business analyst is facilitating a requirements workshop with 12 stakeholders from operations, finance, and IT. Two participants dominate the conversation, while several others remain silent. The BA needs to ensure all voices are heard and gather balanced input on a contentious process change. Which technique should the BA use to structure the discussion and equalize participation?

Medium
267

A project team is working on a construction project. The project manager notices that the actual cost is consistently higher than planned. Which project management process is most directly responsible for monitoring and controlling costs?

Easy
268

A team new to Kanban maps its workflow and discovers that work sits in a 'Code Review' column for many days. The team wants to improve flow without changing its process policies yet. Which Kanban practice should the team apply first to expose the problem and drive improvement?

Hard
269

A project manager is working on a project to develop a new mobile application. The project is in the planning phase. The project manager is creating a document that will describe how the project team will acquire, develop, manage, and release project resources. Which document is the project manager creating?

Medium
270

Which tool is used to visually represent the relationships between requirements and other project artifacts?

Medium
271

Refer to the exhibit. Based on the error log, which task has a dependency issue?

Medium
272

A project team wants to compare their sales order process with that of a leading competitor to identify improvement opportunities. Which technique is best?

Medium
273

Which TWO techniques are commonly used for requirements elicitation? (Choose two.)

Easy
274

A company uses Scrum with two-week sprints. The team's velocity is 30 story points per sprint, and they have a well-refined product backlog. However, stakeholders frequently introduce urgent, high-priority requests mid-sprint, which the Product Owner accepts because of stakeholder pressure. As a result, the team is overcommitted each sprint, often leaving 40% of planned work incomplete. The Product Owner is frustrated because promised features are delayed, and the team feels demotivated due to constant interruptions. The Scrum Master has been asked to intervene. What is the best course of action for the Scrum Master?

Hard
275

An agile team is adopting Extreme Programming (XP). A developer asks how the practice of continuous integration differs from simply building the software nightly. Which statement best describes the XP practice of continuous integration?

Medium
276

A Scrum team has a stable velocity of 30 story points per sprint. The Product Owner requests that the team deliver 50 story points in the next sprint to meet a market deadline. What is the best course of action for the Scrum Master?

Medium
277

The sponsor is concerned about the accuracy of cost estimates prepared using analogous estimating. Which estimating technique should the project manager recommend to improve accuracy?

Hard
278

A business analyst is working on a project to replace a legacy accounting system. The organization operates in a highly regulated environment, and the new system must comply with strict financial reporting standards. The BA needs to ensure that all regulatory requirements are captured and traceable throughout the project lifecycle. Which action best ensures that regulatory requirements are properly managed?

Hard
279

Match each communication method to its characteristic.

Medium
280

A Scrum Master observes that the Development Team consistently overcommits during Sprint Planning and often fails to deliver all committed items by the Sprint Review. What should the Scrum Master do?

Hard
281

A Scrum Master is coaching a team that is struggling with the Sprint Retrospective. The team often focuses only on what went wrong and leaves the meeting without concrete actions. Which two techniques should the Scrum Master suggest to improve the effectiveness of the retrospective? (Choose two.)

Hard
282

A Scrum Team's Sprint Review is consistently a one-way presentation where the Product Owner demos completed features to stakeholders. Stakeholder feedback rarely changes the Product Backlog, and the team feels the event adds little value. What should the Scrum Master do?

Hard
283

A project involves upgrading a legacy financial reporting system. The business analyst (BA) has been assigned to elicit requirements. The BA schedules a series of one-on-one interviews with key stakeholders, but after three interviews, the BA notices that stakeholders are providing inconsistent information. The BA suspects that some stakeholders have hidden agendas and are reluctant to share complete details. The BA recalls that the project sponsor emphasized the need for a comprehensive and accurate requirements set. The BA has limited time and budget. What should the BA do next?

Medium
284

After gathering requirements, the business analyst is prioritizing them based on stakeholder value and implementation complexity. Which tool is commonly used for this purpose?

Easy
285

During project execution, a key stakeholder requests a change that will increase the project scope. The project manager evaluates the impact and determines it will require additional budget and time. What should the project manager do first?

Medium
286

A business analyst is facilitating a requirements workshop. Which technique is best for generating creative ideas?

Easy
287

A project team is troubleshooting a delay in the critical path. The project manager identifies that a non-critical activity has slipped by five days but the project end date remains unchanged. What is the most likely reason for this?

Medium
288

A business analyst at a hospital is facilitating a requirements workshop with physicians, nurses, and IT staff. The goal is to define the data elements required for a new patient intake system. The physicians and nurses have conflicting opinions about which data is essential, and the IT staff is concerned about integration with existing systems. Which technique would be most effective to build consensus and clearly document the data requirements?

Medium
289

A project manager is leading a predictive project to develop a new software application. The project sponsor asks for a document that describes how the project scope will be defined, validated, and controlled. Which two elements should the project manager include in this document? (Choose two.)

Medium
290

A project manager is developing a work breakdown structure (WBS) for a construction project. Which approach should be used to ensure all deliverables are identified?

Easy
291

A business analyst is conducting a requirements elicitation session for a new enterprise resource planning (ERP) system. The BA needs to ensure that the requirements are complete and that all stakeholder perspectives are considered. Which two techniques are most appropriate for eliciting requirements from a large, diverse group of stakeholders across multiple departments? (Choose two.)

Hard
292

A project manager is leading a project to implement a new customer relationship management (CRM) system. The project is in the execution phase. The project manager notices that a team member is consistently late in completing assigned tasks, causing delays. What is the most appropriate action for the project manager to take first?

Easy
293

Which TWO of the following are key responsibilities of a business analyst in the context of project management?

Medium
294

A business analyst reviews existing project documentation, process flows, and system manuals to understand the current environment. This technique is called:

Easy
295

A project manager is leading a large construction project. The project has a fixed-price contract with a penalty clause for late delivery. During execution, a key supplier fails to deliver materials on time, causing a delay. The project manager needs to decide on the best course of action to minimize the impact. Which action should the project manager take first?

Hard
296

Which TWO activities are considered part of Product Backlog refinement? (Select TWO)

Medium
297

Which TWO practices are part of the Scrum framework?

Easy
298

A business analyst is facilitating a requirements workshop for a new HR onboarding system. Attendees include the HR director, two recruiters, an IT security officer, and a payroll supervisor. The HR director dominates the discussion and repeatedly redirects every topic toward executive reporting dashboards, while the recruiters' process concerns go unrecorded. Which facilitation technique should the business analyst apply to ensure balanced input before documenting requirements?

Medium
299

During requirements prioritization, the business analyst receives conflicting input from stakeholders. Which technique should be used to reach a consensus?

Medium
300

A project is in the executing phase, and the team is frequently reworking deliverables due to defects. Which process is most likely inadequate?

Hard
301

A project team is adopting Kanban. They currently have a cycle time of 10 days and a throughput of 5 items per week. The team wants to improve predictability. Which action would most directly help?

Medium
302

A business analyst is facilitating a requirements prioritization session for a new e-commerce platform. The project has a strict deadline and limited resources. Which prioritization technique should be used to maximize value delivered within constraints?

Hard
303

During a project’s initiation phase, the business analyst is conducting a stakeholder analysis. Which technique is most appropriate for categorizing stakeholders based on their power and interest?

Easy
304

A team is struggling with frequent requirement changes during a Sprint. The Product Owner keeps adding new items. What should the Scrum Master do?

Hard
305

Which TWO of the following are typically outputs of the Initiating process group?

Easy
306

A business analyst is facilitating a requirements workshop for a new payment system. The workshop includes representatives from sales, finance, IT, and customer support. During the session, the sales team insists on supporting multiple currencies, while finance emphasizes strict audit trails. IT wants a microservices architecture, but customer support demands a simple user interface. The conversation becomes heated, and no decisions are made. The project sponsor wants a single recommendation that balances these needs. As the business analyst, what is the best approach to move forward?

Hard
307

A business analyst is evaluating a proposed solution and discovers that it does not fully address the root cause of the business problem. What should the analyst do next?

Hard
308

During a requirements validation session, the project sponsor questions whether a particular requirement aligns with the business case. The business analyst recalls that the requirement originated from a regulatory compliance need. What should the BA do to resolve the concern?

Medium
309

During a project, multiple stakeholders have conflicting requirements for a new software feature. The business analyst needs to prioritize the requirements to ensure the most critical ones are delivered first. Which technique is most appropriate for prioritizing requirements?

Medium
310

A business analyst is assessing the feasibility of a proposed solution that involves integrating a new mobile app with an existing legacy system. The legacy system has no documented APIs and uses a proprietary protocol. Which factor is most critical to evaluate when determining technical feasibility?

Hard
311

A business analyst is reviewing the output of a requirements validation session. The following issues were identified: 'Requirement REQ-001 has no associated business objective', 'Requirement REQ-002 has a conflicting priority with REQ-003'. What is the most likely cause of these issues?

Hard
312

A project team using a Kanban board wants to predict when all remaining backlog items will be completed. Which metric is most useful for this prediction?

Hard
313

Which TWO of the following are considered key constraints in project management that form the traditional 'triple constraint'?

Medium
314

During requirements gathering, the BA wants to ensure that each requirement can be traced back to its origin. Which tool is best for this purpose?

Easy
315

A project manager notices that the team is frequently redoing work because requirements were unclear. Which process group interaction would help address this issue?

Hard
316

A business analyst is conducting a needs assessment for a new software system. Which of the following is the primary purpose of this activity?

Easy
317

During a predictive project's execution phase, a key stakeholder requests a change that adds a minor feature. The project manager assesses the impact and determines the change will increase cost by 5% and extend the schedule by two days, which is within the contingency reserves. What should the project manager do first?

Medium
318

A software development project is facing high uncertainty in requirements. The team is experienced and prefers frequent feedback. Which project life cycle approach is most appropriate?

Hard
319

Which TWO statements about the Sprint Backlog are true? (Select TWO)

Medium
320

You are a business analyst on a project to upgrade the network infrastructure in a large organization. The project plan was created using a predictive approach, and requirements were gathered months ago. During implementation, the team discovers that some requirements conflict with a new company-wide security policy issued after the project started. The project manager says the scope is frozen and changes cannot be accommodated. The sponsor is not involved daily. As the business analyst, what is the most effective action to take?

Medium
321

A business analyst needs to understand how users currently perform a task before designing a new system. Which elicitation technique is best for capturing step-by-step processes in the actual work environment?

Easy
322

A business analyst is defining the scope of a project to replace a legacy billing system. The sponsor wants to know which capabilities are included and which are not. Which tool or technique should the BA use to clearly document the boundaries of the solution?

Medium
323

A software development project is using a predictive approach with a detailed project schedule based on the critical path method (CPM). The project is currently in the execution phase. The team reports that a critical task (Task X) is two weeks behind schedule. Task X has a total float of 0 and has two immediate successors: Task Y and Task Z, both of which are also on the critical path. The project manager has the ability to add resources to overlapping tasks. The project sponsor is concerned about the schedule delay and wants a recovery plan. The project manager needs to determine the best course of action to get the project back on track without impacting quality or budget excessively.

Medium
324

Which THREE are formal Scrum ceremonies (events) as defined in the Scrum Guide?

Medium
325

After deploying a new CRM system, the project team measures user adoption rates, number of support tickets, and average response time. This activity belongs to which business analysis domain?

Medium
326

Refer to the exhibit. What is the total float of Task B?

Medium
327

A business analyst is working on a regulatory compliance project with many diverse stakeholders. The analyst needs to categorize stakeholders based on their interest and influence to prioritize engagement. Which tool should the analyst use?

Hard
328

A project manager is leading a requirements workshop for a new software system. The business analyst suggests using a technique that involves creating a visual representation of the sequence of steps in a business process. Which technique is being suggested?

Medium
329

Refer to the exhibit. A business analyst is troubleshooting a performance issue reported by users. The ping and traceroute show successful connectivity to the server at 10.0.0.1. Despite this, the application response is slow. Which analysis step should the analyst take next?

Hard
330

Refer to the exhibit. The team's velocity is 30 points per sprint, and they have already committed to stories totaling 22 points. What is the team's remaining capacity for this sprint?

Easy
331

Which TWO of the following are considered examples of enterprise environmental factors (EEFs)?

Medium
332

A business analyst is planning stakeholder engagement for a new regulatory compliance project. To ensure stakeholder buy-in and minimize risks, when should the business analyst involve key stakeholders?

Easy
333

Which THREE are components of the project management plan?

Easy
334

A project team is using a colocation (war room) technique. What is the primary benefit?

Easy
335

You are a senior business analyst on a multi-year program to overhaul the customer service operations. The program uses a tailored framework combining elements from BABOK and Agile. During the transition phase, you discover that the requirements traceability matrix is incomplete; many requirements are not linked to test cases or business objectives. The project manager is concerned about regulatory compliance and wants to ensure all requirements are validated. The testing team is falling behind schedule. As the business analyst, what is the most critical action to take?

Hard
336

A team is new to Agile and wants to implement a framework that emphasizes iterative development, time-boxed iterations, and a prioritized backlog. Which framework should they adopt?

Easy
337

A team is transitioning to Kanban. Which TWO principles should they adopt? (Choose two)

Hard
338

In a predictive project management approach, which TWO artifacts are components of the project management plan?

Medium
339

A project is behind schedule and over budget. The sponsor asks the project manager to reduce costs without affecting the end date. Which constraint should the project manager consider adjusting?

Medium
340

A project manager is developing the project management plan for a predictive project to implement a new ERP system. The sponsor asks which components are typically included in the project management plan. (Choose two.)

Medium
341

Which THREE activities are part of the Sprint Planning meeting in Scrum?

Medium
342

A project manager is assigned to a project in a functional organization. The project team members report to their functional managers and only work on the project part-time. The project manager has little authority and must rely on the functional managers for resource decisions. Which challenge is the project manager MOST likely to face?

Medium
343

Which of the following best defines a project?

Easy
344

A business analyst is validating requirements for a loan origination system. A requirement states that the system must be user-friendly. During validation, the analyst recognizes this requirement cannot be tested. Which action should the analyst take to make the requirement verifiable?

Medium
345

An organization is considering a new software development project. The business analyst is asked to determine if the project is financially viable. Which analysis is most appropriate?

Hard
346

A project manager is leading a project to implement a new customer relationship management (CRM) system. The project manager is identifying stakeholders and wants to ensure all key stakeholders are engaged. Which two statements accurately describe stakeholder management? (Choose two.)

Medium
347

A business analyst is creating a business case for a new project. Which of the following is a key component that must be included in the business case?

Hard
348

A project manager is evaluating cost performance using earned value management (EVM). The project has a cost performance index (CPI) of 0.85 and a schedule performance index (SPI) of 0.90. Which conclusion is most appropriate?

Hard
349

A project manager is leading a project to develop a new mobile application. The project sponsor asks for a document that formally authorizes the project and gives the project manager authority to apply organizational resources to project activities. Which document should the project manager provide?

Medium
350

A project manager is working on a research and development project where the scope is not clearly defined at the start. The project manager wants to use an adaptive approach to manage the project. Which two characteristics are typical of an adaptive project management approach? (Choose two.)

Hard
351

Refer to the exhibit. A business analyst is reviewing the requirements status in a JSON export from a requirements management tool. The analyst notices that REQ02 is still in 'Draft' while REQ01 is 'Approved'. What should the analyst do next?

Medium
352

A newly formed agile team is about to start their first sprint. The product owner has a well-groomed backlog and the team has done relative sizing using planning poker. The team is excited but unsure about the process. They ask the Scrum Master what the primary goal of the first iteration should be. The Scrum Master should explain that the most important goal of the first sprint is to deliver a potentially releasable increment of the product. However, some team members are worried they may not be able to deliver enough due to team formation and learning the codebase. The product owner wants to see a visible outcome. What should the Scrum Master recommend as the primary focus for the first sprint?

Easy
353

Which TWO are core practices of Extreme Programming (XP)?

Hard
354

A project manager is planning a project and needs to identify all the work required to complete the project successfully. Which document is the primary output of the Create WBS process?

Easy
355

The team notices that work is piling up in the Testing column. The WIP limit for Testing is 3, but currently there are 5 items. What should the team do first?

Medium
356

In a predictive project life cycle, which of the following best describes the relationship between scope, time, and cost?

Hard
357

A business analyst needs to capture and manage requirements throughout the project lifecycle. Which artifact is most suitable for this purpose?

Easy
358

Which THREE of the following are recognized process groups in the PMBOK Guide? (Choose three)

Medium
359

A project manager is assigned to a cross-functional initiative in a matrix organization. The team members report to both the project manager and their functional managers. What is the primary challenge the project manager would face?

Medium
360

A business analyst is preparing a requirements traceability matrix (RTM) for a regulatory compliance project. The project manager asks how the RTM will help when a new regulation is introduced late in the project. What is the primary benefit of maintaining the RTM in this situation?

Hard
361

You are a business analyst conducting a stakeholder analysis for a project that will affect multiple departments. You need to determine how to engage stakeholders effectively. Which two techniques are most appropriate for identifying and prioritizing stakeholders? (Choose two.)

Medium
362

A business analyst is defining the solution scope for a project replacing a legacy claims system. The sponsor wants to include every capability the claims department might eventually need, while the operations manager wants to limit the release to core adjudication only. The analyst must recommend an approach that keeps the project deliverable while preserving future options. Which action best applies business analysis scope principles?

Hard
363

Which THREE of the following are typically included in a business case?

Medium
364

A project manager is preparing to close a project that has delivered its final product. The customer has formally accepted the deliverable. Which of the following should the project manager do NEXT?

Easy
365

A project manager is developing the project schedule for a construction project. The team has identified that the foundation work must be completed before the framing can begin. Which type of dependency does this represent?

Medium
366

A project manager is developing the project charter for a new office relocation project. The sponsor has provided a high-level description of the business need. Which input is essential for developing the project charter?

Easy
367

An Agile team is experiencing frequent changes in requirements from stakeholders. Which approach best enables the team to adapt while maintaining productivity?

Hard
368

A project manager is leading a software development project using a predictive plan-based methodology. The project is at 70% completion and the team has discovered a significant defect in a module that was completed two months ago. The defect was not identified during testing because the test cases were incomplete. The project schedule has a buffer of 5 days, and the defect is expected to take 10 days to fix. The project manager needs to determine the best course of action. Which of the following should the project manager do?

Easy
369

You are managing a software upgrade project for a financial institution. The project involves upgrading the core banking system to a new version. During user acceptance testing (UAT), the testers find that the new system does not handle certain legacy data formats correctly, causing errors. The project schedule has no buffer left, and the go-live date is fixed due to regulatory compliance. The team estimates it will take two weeks to fix the issue, but the go-live is in one week. The project manager has already used the contingency reserve for other issues. What should the project manager do next?

Medium
370

Which THREE of the following are components of the project charter?

Medium
371

A project manager needs to decompose the project scope into smaller, more manageable components to provide a framework for detailed planning. Which technique should the project manager use?

Easy
372

A project team is experiencing frequent changes in requirements. The project manager wants to minimize disruptions. Which approach is best to manage changes effectively?

Easy
373

A startup is developing a mobile application with rapidly changing requirements. The team needs to deliver value quickly and adapt to user feedback. Which business analysis approach is most appropriate?

Easy
374

A project manager is reviewing the project's cost performance. The actual cost (AC) is $50,000, the earned value (EV) is $45,000, and the planned value (PV) is $60,000. What is the cost variance (CV)?

Medium
375

During project execution, you notice that a key stakeholder, the head of the legal department, has been disengaged from project reviews and has not responded to your emails requesting input on a regulatory compliance issue. The project is at risk of missing a legal requirement that could result in fines. You have classified this stakeholder as having high power and high interest. According to stakeholder engagement best practices, what should you do first?

Medium
376

A project manager is leading a software development project using a predictive life cycle. The project is in the execution phase. Which two of the following activities are typically performed during this phase? (Choose two.)

Hard
377

A Scrum team is preparing for its Sprint Review. The Product Owner wants to know which artifacts the team should present to stakeholders to demonstrate the completed work. What is the most appropriate focus for the Sprint Review?

Easy
378

A project manager is working on a construction project with a fixed-price contract. The project is in the execution phase, and a key supplier has failed to deliver critical materials on time, causing a delay. The project manager needs to address this issue and prevent further delays. Which action should the project manager take FIRST?

Hard
379

Refer to the exhibit. Which critical element is missing from this business case?

Hard
380

You are a project manager in a projectized organization. The project is nearing completion, but a key stakeholder has introduced several new requirements that were not in the original scope. The stakeholder insists these are critical for user acceptance. The project is already behind schedule and over budget. The change control board (CCB) has denied all previous change requests due to time and cost constraints. What is the best course of action?

Hard
381

During the planning phase of a predictive project, the project manager wants to define the project scope more precisely. Which process should be used to develop a detailed description of the project and product?

Hard
382

During project execution, a key stakeholder requests a change that will increase the project scope. The project manager evaluates the impact and determines it will require additional budget and time. What is the first step the project manager should take?

Easy
383

Which TWO statements correctly describe characteristics of the Kanban method?

Medium
384

A project manager is leading a predictive software implementation project. The project sponsor asks for a document that lists all the work that must be completed to deliver the product, organized in a hierarchical decomposition. Which document should the project manager provide?

Easy
385

A project manager is leading a team that includes members from different cultures. Communication misunderstandings are causing delays. Which action best addresses the root cause?

Medium
386

During requirements elicitation, the team discovers conflicting needs from two key stakeholders. The project manager asks the business analyst to use a prioritization technique that allows stakeholders to vote anonymously to reach consensus. Which technique should be used?

Hard
387

A project manager is working on a project in a functional organization. The project manager needs to assign a team member to a critical task, but the functional manager insists that the team member work on a different departmental priority. The project manager has little authority over resources. Which of the following best describes the likely outcome?

Medium
388

A project manager is defining success criteria for a new software development project. Which of the following is the most objective and measurable success criterion?

Easy
389

Which of the following is a key output of the needs assessment process?

Easy
390

A Scrum team is in the middle of a Sprint when a critical production bug is discovered. The Product Owner wants the team to fix it immediately, but the team is concerned about disrupting the Sprint Goal. What is the most appropriate action according to Scrum?

Medium
391

A project has a fixed deadline but flexible scope. The project manager receives a change request that would significantly increase scope. What should the project manager do first?

Medium
392

During a requirements elicitation meeting, stakeholders provide conflicting information about the desired functionality. What is the best course of action for the business analyst?

Easy
393

In project procurement management, what is the primary purpose of the procurement statement of work (SOW)?

Medium
394

During stakeholder analysis, a business analyst identifies a key stakeholder who rarely speaks in meetings but provides detailed written feedback. Which engagement strategy is most appropriate?

Medium
395

During project execution, a key stakeholder requests a significant change that will increase project scope. The project manager performs an impact analysis and determines that the change will delay the project by two weeks and increase costs by 10%. However, the change is critical for regulatory compliance. What should the project manager do first?

Hard
396

A project manager is planning a data-center migration that will use a predictive life cycle. The project has a hard regulatory deadline, and the sponsor wants confidence that the schedule is achievable before authorizing funding. The project manager has already decomposed all work packages and estimated activity durations and resource requirements. Which action should the project manager take NEXT to determine whether the deadline can realistically be met?

Medium
397

Which THREE techniques are commonly used for requirements elicitation?

Hard
398

Which of the following is a key component of a project scope baseline in predictive project management?

Medium
399

Which is an effective way to prioritize user stories in a product backlog?

Easy
400

A project manager is developing the project management plan for a new payroll system implementation. The sponsor wants assurance that stakeholder expectations are documented and managed throughout the project. Which TWO documents or components should the project manager create to address this need? (Choose two.)

Medium
401

A project manager is assigned to a project that is in execution phase. The project has a cost performance index (CPI) of 0.8 and a schedule performance index (SPI) of 1.1. Which of the following best describes the current status of the project?

Hard
402

A project manager is reviewing the project charter and notices that the business case includes a cost-benefit analysis with a Net Present Value (NPV) of $50,000 and an Internal Rate of Return (IRR) of 12%. The company's required rate of return is 10%. What should the project manager conclude about this project?

Medium
403

Which practice is a key component of Extreme Programming (XP)?

Medium
404

An Agile team consistently completes only about 70% of the planned work each sprint. Which action is most likely to improve the team's ability to meet commitments?

Medium
405

A business analyst is creating a data model for a new human resources system. The BA needs to represent the relationships between employees, departments, and job positions. Which type of diagram is most appropriate for this purpose?

Easy
406

A business analyst is preparing a requirements traceability matrix for a regulatory compliance program at a bank. The matrix must link business needs to solution components across the project life cycle. Which two relationships should the traceability matrix capture to support both scope verification and impact analysis of future change requests? (Choose two.)

Hard
407

A project manager is preparing to close a project that has successfully delivered its product. The project manager must ensure that all project work is completed and that the project is formally closed. Which process group includes the activities to finalize all activities across all process groups and formally close the project?

Medium
408

After solution implementation, the business analyst discovers that a key performance indicator (KPI) has not improved as expected. What is the most appropriate next step?

Hard
409

A business analyst is planning a requirements elicitation session for a new enterprise resource planning (ERP) system. The project has stakeholders in three countries with different time zones and conflicting opinions. The BA wants to reduce the influence of dominant personalities and obtain honest input from all participants. (Choose two.)

Hard
410

A project manager is developing a project schedule for a software development project using a predictive approach. After identifying activities and sequencing them, what is the NEXT step?

Easy
411

During project execution, a key team member leaves the company. The project manager needs to quickly reassign tasks to maintain progress. Which document should be consulted first to understand the team member's current responsibilities?

Medium
412

A project manager is leading a construction project with a fixed budget and strict deadline. During execution, a key supplier notifies that a critical material will be delayed by two weeks, which will push the project past the deadline. The project manager reviews the schedule and identifies that the delay can be compensated by fast-tracking two subsequent activities that are currently planned sequentially. What should the project manager do first?

Medium
413

A software development team is transitioning from a plan-driven approach to Scrum. The Product Owner is enthusiastic but struggles to break down the product backlog into small, independent items. The team frequently encounters dependencies between user stories, causing delays in sprints. What is the best course of action for the Scrum Master to address this issue?

Hard
414

A project manager is executing a predictive project to build a data center. The project is halfway complete, and the project manager is analyzing cost performance. The earned value (EV) is $500,000, the planned value (PV) is $600,000, and the actual cost (AC) is $550,000. The project manager needs to forecast the total cost at completion, assuming the current cost performance will continue. Which earned value management (EVM) metric should the project manager use to determine the estimate at completion (EAC)?

Hard
415

A team is using Scrum and notices that the Product Owner frequently changes priorities during the Sprint, causing the team to rework tasks. What should the Scrum Master do first?

Medium
416

A project manager is assigned a project that has a very low tolerance for scope changes. Which development approach is most appropriate?

Easy
417

Your organization is initiating a new mobile app development project. The product owner expects to release a minimum viable product (MVP) within three months, with subsequent iterations based on user feedback. The development team is experienced with agile methodologies. The project sponsor, however, is accustomed to traditional waterfall projects and insists on a detailed upfront plan covering all requirements and a fixed schedule. You need to select a project life cycle that balances the product owner's desire for iterative delivery with the sponsor's need for predictability. What is the most appropriate approach?

Easy
418

A business analyst discovers that two requirements conflict with each other. What is the best strategy to resolve this conflict?

Medium
419

A project manager is leading a website redesign project. The sponsor asks, 'What is the difference between a project and ongoing operations?' Which of the following best describes a project?

Easy
420

A project manager is developing the project schedule for a construction project. The team has identified all activities and their dependencies. Which tool should the project manager use to determine the critical path?

Easy
421

A project manager is using a predictive approach for an aircraft component project. The team has identified a risk that a critical supplier may fail to deliver a specialized alloy on time. The project manager wants to reduce the probability and impact of this risk by taking action before it occurs. Which risk response strategy should the project manager use?

Hard
422

During Sprint Planning, the team realizes the password reset story involves a third-party email service that has not been integrated yet. The team has no experience with that service. What is the best action?

Hard
423

Which TWO of the following are commonly used requirements elicitation techniques?

Easy
424

Refer to the exhibit. A business analyst has documented the current and target states for invoice processing. What business analysis technique is being used?

Easy
425

You are a business analyst facilitating a workshop to define the future-state processes for a customer onboarding system. Participants include operations staff, IT, and compliance. Which technique should you use to ensure all perspectives are captured and the group reaches a shared understanding of the new process?

Hard
426

A financial services company is adopting Scrum for a critical compliance project. The team has six developers, one product owner, and one Scrum Master. After three sprints, the product owner is frustrated because the team has only delivered 40% of the planned features. The team says they are working full capacity but keep getting interrupted by urgent production support requests from the operations team. The Scrum Master notices that the team’s velocity is dropping each sprint. The product owner insists on increasing the sprint length from two weeks to four weeks to allow more time for delivery. However, the compliance deadline is fixed. The Scrum Master must recommend a course of action. What should the Scrum Master do?

Hard
427

In Kanban, the team is experiencing frequent bottlenecks at the testing stage. Which practice should they adopt to improve flow?

Easy
428

You are the project manager for a large infrastructure project using a predictive plan-based methodology. The project has a critical path duration of 200 days. After 50 days of execution, a major delay occurs on a critical path activity due to unforeseen ground conditions, adding 20 days to that activity. The project has no float on the critical path. The sponsor requests a recovery plan to bring the project back on schedule. The team proposes two options: (1) crash activity X on the critical path by adding overtime, costing $10,000 and saving 5 days; (2) fast-track activity Y and Z by starting Y earlier, saving 10 days but increasing risk. What is the BEST integrated approach?

Hard
429

A team using Scrum has a velocity of 30 story points per Sprint. The Product Owner wants to plan for the next release with 150 story points of work remaining. The team is stable. Which release planning approach aligns with agile principles?

Hard
430

In a Kanban system, what is the primary purpose of limiting Work in Progress (WIP)?

Easy
431

Which TWO of the following are true regarding a project's life cycle?

Medium
432

A project manager is leading a project to implement a new enterprise resource planning (ERP) system. During the execution phase, the project manager notices that team members are spending a significant amount of time resolving conflicts and clarifying roles. To improve team performance, the project manager decides to focus on team development. Which action should the project manager take first?

Hard
433

A project manager is creating the project schedule. The team estimates that the optimistic time for an activity is 10 days, the pessimistic time is 30 days, and the most likely time is 15 days. Using PERT three-point estimation, what is the expected duration?

Easy
434

A business analyst is selecting a business analysis framework for a small project with limited budget. Which framework characteristic is most important to consider?

Easy
435

A business analyst is working on a project to develop a mobile banking application. During the requirements analysis phase, the BA creates a set of user stories and acceptance criteria. The BA then conducts a peer review with the development team. The team points out that the stories are too large and vague to estimate. The BA needs to refine the requirements to make them actionable. The project is using an agile methodology with two-week sprints. What should the BA do?

Easy
436

In a project to implement a new customer relationship management (CRM) system, the business analyst needs to understand the current workflows and identify areas for improvement. Which technique should be used?

Medium
437

A project manager is estimating activity durations for a software development project. The team has historical data from similar projects, but the current project involves new technology that could cause delays. Which estimating technique should the project manager use to account for uncertainty?

Hard
438

In a Kanban system, the team notices that work items are spending too much time in the 'In Progress' column. Which practice should the team adopt to improve flow?

Medium
439

A Product Owner frequently misses backlog refinement sessions, leaving user stories vague. The Development Team is struggling to estimate and plan Sprints. What fundamental Scrum role is being neglected?

Medium
440

A project manager is leading a construction project to build a new bridge. The project sponsor asks the project manager to create a document that formally authorizes the project and gives the project manager the authority to apply organizational resources to project activities. Which document should the project manager produce?

Medium
441

A project manager notices that the project's cost performance index (CPI) is 0.85. What does this indicate?

Medium
442

Which TWO of the following are valid techniques for schedule compression in a predictive project?

Hard
443

In a predictive project, the project manager must formally accept the project's deliverables. Which process group does this activity belong to?

Medium
444

A business analyst is using a business analysis framework to identify stakeholders. Which technique is most effective for ensuring all affected parties are considered?

Easy
445

A business analyst is working on a project to implement a new human resources software. The project is using an Agile framework with two-week sprints. After three sprints, the product owner is frustrated because the team has not delivered any working functionality that can be demoed. The business analyst realizes that the user stories lack acceptance criteria and are too large to complete in a sprint. The team is also spending too much time on documentation. As the business analyst, what should you do to improve the situation?

Medium
446

A Scrum team is struggling with its Daily Scrum. The Scrum Master notices that the meeting often runs long, turns into a status report to the Scrum Master, and does not result in a clear plan for the next 24 hours. Which two actions should the Scrum Master take to improve the Daily Scrum? (Choose two.)

Medium
447

An agile team using Scrum has a Definition of Done that requires automated regression tests to pass. A developer argues that a small bug fix should be released without running the full suite because the change is trivial. What is the most appropriate response?

Medium
448

A project manager is estimating activity durations for a new software development project. The manager has data from three similar previous projects, but the new project is slightly larger in scope. Which estimating technique is most appropriate given the available data?

Hard
449

Which THREE factors should a business analyst consider when selecting an elicitation technique for a project?

Hard
450

A project manager is working on a predictive project to develop a new medical device. The project sponsor asks for a document that describes how the project team will implement the quality policies of the performing organization. Which document should the project manager provide?

Easy
451

In Extreme Programming (XP), which practice involves integrating and testing the entire system multiple times per day?

Easy

Frequently asked questions

What does the scenario questions domain cover on the CAPM exam?
scenario questions questions test whether you can apply the concept in context, not just recognise a definition.
How many questions are in this domain?
This page lists all 451 scenario questions questions in the CAPM question bank. The actual exam draws from this domain proportionally to its weighting in the official exam blueprint.
What is the best way to practise this domain?
Start with a short focused session (10 questions) to identify gaps, then work through explanations. Repeat with a longer session once the weak areas feel solid.
Can I practise only scenario questions questions?
Yes — the session launcher on this page filters questions to this domain only. Choose any session length for inline explanations and scoring.