Courseiva

CAPM Business Analysis Frameworks Practice Question

A startup is developing a mobile application with rapidly changing requirements. The team needs to deliver value quickly and adapt to user feedback. Which business analysis approach is most appropriate?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Agile

Agile is designed for rapid iteration and adaptability to changing requirements.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    V-Model

    Why it's wrong here

    The V-Model pairs each development stage with a corresponding verification stage, fixing requirements before build begins, so late feedback cannot reshape scope. It suits regulated hardware or safety-critical projects demanding documented traceability. A startup needing rapid iteration and user-driven change cannot accommodate that sequential verification structure.

  • ✓

    Agile

    Why this is correct

    Agile's iterative, time-boxed increments let the team reprioritise a evolving backlog each sprint, directly satisfying the stem's rapidly changing requirements and need for quick value delivery. Unlike predictive approaches, working software is released frequently, so user feedback shapes subsequent iterations rather than being deferred to a single end-stage acceptance phase.

  • ✗

    Spiral

    Why it's wrong here

    The Spiral model’s risk-driven iterative cycles are designed for large-scale, high-risk systems where formal risk analysis precedes each phase, not for rapidly changing requirements in a startup. It is tempting because its iterative nature resembles agile feedback loops, but Spiral’s heavy documentation and risk-assessment overhead would delay value delivery. It would be correct for a safety-critical project, such as medical-device software, where mitigating identified risks outweighs speed.

  • ✗

    Waterfall

    Why it's wrong here

    Waterfall completes requirements, design, build and test as distinct sequential phases, so feedback arriving after delivery cannot alter the current increment. It fits fixed-scope, well-understood work such as construction or compliance projects. Rapidly changing mobile requirements demand iterative delivery instead.

About these practice questions

One of 451 original CAPM practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.