Question 291 of 503
Project Management Fundamentals and Core ConceptsmediumMultiple ChoiceObjective-mapped

Quick Answer

The answer is T2. The error log explicitly states 'Dependency not met for T2: predecessor T1 not completed,' which means T2 cannot start because its finish-to-start predecessor, T1, is still unfinished—a direct violation of the logical sequence defined in the project schedule. This tests your ability to read error logs and map them to dependency types, a common scenario on the CAPM exam where you must identify schedule logic failures rather than just memorizing definitions. A frequent trap is confusing a successor’s dependency issue with a predecessor’s delay; here, the problem belongs to T2, not T1. Remember the mnemonic: "The successor suffers when the predecessor stumbles."

CAPM Practice Question: Project Management Fundamentals and Core Concepts

This CAPM practice question tests your understanding of project management fundamentals and core concepts. The scenario asks you to isolate a root cause — eliminate options that address a different problem before choosing. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

Exhibit

2023-05-10 14:22:33 ERROR: Task T2 - dependency not met: Predecessor task T1 not completed.
2023-05-10 14:25:12 WARN: Task T3 - resource overallocation detected.
2023-05-10 14:30:45 ERROR: Task T4 - schedule variance exceeded threshold.

Refer to the exhibit. Based on the error log, which task has a dependency issue?

Question 1mediummultiple choice
Full question →

Exhibit

2023-05-10 14:22:33 ERROR: Task T2 - dependency not met: Predecessor task T1 not completed.
2023-05-10 14:25:12 WARN: Task T3 - resource overallocation detected.
2023-05-10 14:30:45 ERROR: Task T4 - schedule variance exceeded threshold.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

T2

The error log shows 'Dependency not met for T2: predecessor T1 not completed'. This indicates T2 has a dependency issue because its predecessor task (T1) has not finished, violating the logical relationship defined in the project schedule. In project management, a finish-to-start dependency requires the predecessor to be 100% complete before the successor can begin.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • T3

    Why it's wrong here

    T3 has a resource overallocation warning, not a dependency issue.

  • T1

    Why it's wrong here

    T1 is the predecessor mentioned, but the issue is with T2.

  • T4

    Why it's wrong here

    T4 has a schedule variance error, not a dependency issue.

  • T2

    Why this is correct

    The log shows 'Task T2 - dependency not met'.

    Related concept

    Read the scenario before looking for a memorised answer.

Common exam traps

Common exam trap: answer the scenario, not the keyword

PMI often tests the distinction between which task has the dependency issue (the successor) versus which task is causing the issue (the predecessor), leading candidates to incorrectly select the predecessor task (T1) instead of the successor (T2).

Detailed technical explanation

How to think about this question

In project scheduling, dependency issues often arise from incorrect predecessor-successor relationships, such as finish-to-start (FS), start-to-start (SS), or finish-to-finish (FF). The error log indicates a FS dependency where T1 must finish before T2 starts. Under the hood, project management software validates these constraints during schedule calculation; if a predecessor is incomplete, the successor's early start date is pushed out, potentially causing critical path delays. In real-world scenarios, this is common when tasks are added or modified without updating dependencies, leading to resource overallocation or missed milestones.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the CAPM exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related CAPM practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free CAPM practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this CAPM question test?

Project Management Fundamentals and Core Concepts — This question tests Project Management Fundamentals and Core Concepts — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: T2 — The error log shows 'Dependency not met for T2: predecessor T1 not completed'. This indicates T2 has a dependency issue because its predecessor task (T1) has not finished, violating the logical relationship defined in the project schedule. In project management, a finish-to-start dependency requires the predecessor to be 100% complete before the successor can begin.

What should I do if I get this CAPM question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 30, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.