Courseiva
Agile Frameworks and MethodologieshardMultiple ChoiceObjective-mapped

CAPM Agile Frameworks and Methodologies Practice Question

During a Scrum sprint, the development team discovers that a critical dependency on another team's API cannot be resolved until the next sprint. The product owner insists on delivering the current sprint goal without adjusting scope. The team is struggling to meet the definition of done. What should the Scrum Master do first?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Facilitate a discussion between the product owner and team to renegotiate the sprint goal

The Scrum Master should facilitate a discussion with the product owner and team to explore options, such as removing the blocked work or adjusting the sprint goal. The Scrum Master is a servant leader who helps the team and product owner negotiate scope. Ordering the team to work overtime violates Scrum principles. Escalating to management bypasses the Scrum framework. Ignoring the impediment would lead to failure.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Order the team to work overtime to complete the remaining work

    Why it's wrong here

    Mandating overtime is not agile; it reduces quality and morale.

  • Ignore the dependency and ask the team to do their best

    Why it's wrong here

    Ignoring impediments is not proactive; the Scrum Master should address them.

  • Escalate the issue to the program manager for resolution

    Why it's wrong here

    Escalation should be a last resort; the Scrum Master should first facilitate a discussion within the team.

  • Facilitate a discussion between the product owner and team to renegotiate the sprint goal

    Why this is correct

    The Scrum Master coaches the team and product owner to collaborate on scope adjustments when dependencies block work.

Visual reference

Client Recursive Resolver Root DNS (13 root servers) TLD DNS (.com, .org, …) Authoritative example.com query IP addr answer

About these practice questions

Courseiva writes every CAPM question from scratch — 487 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more way this is tested on CAPM

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. During a sprint, the team identifies a critical defect that requires immediate attention. What should the Scrum Master do?

hard
  • A.Report to management.
  • B.Add the defect to the product backlog.
  • C.Allow the team to fix the defect within the sprint if possible.
  • D.Stop the sprint and restart.

Why C: The Scrum Master should facilitate the team to self-organize and address the critical defect within the current sprint if it does not compromise the sprint goal. Option A is wrong because reporting to management is not the Scrum Master's immediate action; the team handles the work. Option B is wrong because adding the defect to the product backlog would delay the fix, and urgent defects are best handled within the sprint. Option D is wrong because stopping the sprint is a drastic measure that should be reserved for extreme situations, not a typical response to a defect.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.