CAPM Practice Question: Project Management Fundamentals and Core Concepts
Which TWO of the following are considered examples of enterprise environmental factors (EEFs)?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Government regulations
Options A and C are correct because company culture and government regulations are external or internal factors that affect the project but are not part of organizational process assets. Lessons learned and templates are organizational process assets. The project charter is an output of the project.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Government regulations
Why this is correct
Government regulations are external EEFs that the project must comply with.
- ✗
Project charter
Why it's wrong here
The project charter is a project document, not an EEF.
- ✓
Company culture
Why this is correct
Company culture is an internal EEF that influences how the project is managed.
- ✗
Lessons learned from previous projects
Why it's wrong here
Lessons learned are organizational process assets, not EEFs.
- ✗
Work breakdown structure template
Why it's wrong here
Templates are organizational process assets.
Go deeper
Related to this question
About these practice questions
Courseiva writes every CAPM question from scratch — 487 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.