CAPM Practice Question: Project Management Fundamentals and Core Concepts
Which TWO of the following are considered examples of enterprise environmental factors (EEFs)?
⚠ Common exam trap
CAPM often tests the confusion between EEFs and OPAs, causing candidates to misclassify internal templates or lessons learned as EEFs when they are actually OPAs.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Government regulations
Government regulations (A) are a classic enterprise environmental factor because they are external constraints imposed on the project that the team cannot change, such as legal, regulatory, or industry compliance requirements. Company culture (C) is also an EEF since organizational culture, structure, and governance are internal environmental conditions that influence how projects are executed but are not under the project manager's direct control. Project charter (B) is a project document that formally authorizes the project, not an environmental factor. Lessons learned from previous projects (D) are part of organizational process assets, not EEFs. Work breakdown structure template (E) is also an organizational process asset because it is a reusable template from the organization's process assets library.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Government regulations
Why this is correct
Government regulations qualify as enterprise environmental factors because they originate outside the project team and constrain how the project may be executed, satisfying the stem's requirement for external influences. Unlike organisational process assets, which are internal and developed within the performing organisation, EEFs such as legal mandates are imposed upon it and cannot be modified by the project manager.
- ✗
Project charter
Why it's wrong here
The project charter is a project document created by the performing organisation, not an environmental factor. It tempts because it originates outside the project team, but EEFs are conditions such as culture, market conditions or infrastructure that influence the project, whereas the charter is an input artefact.
- ✓
Company culture
Why this is correct
Enterprise environmental factors are conditions outside the project team's control that influence how the project is run. Company culture is an internal organisational EEF, shaping communication, decision-making and authority, so it satisfies the stem's requirement for a valid EEF example.
- ✗
Lessons learned from previous projects
Why it's wrong here
Lessons learned from previous projects are an organisational process asset, not an enterprise environmental factor. It tempts because they originate outside the current project, but OPAs are internal organisational knowledge, whereas EEFs are external conditions such as industry standards, culture or economic factors.
- ✗
Work breakdown structure template
Why it's wrong here
A work breakdown structure template is an organisational process asset, not an enterprise environmental factor. It tempts because it comes from outside the project, but OPAs are internal templates, processes and knowledge bases, while EEFs are external conditions like regulations, market conditions or geography.
Go deeper
Related to this question
About these practice questions
Courseiva writes every CAPM question from scratch — 451 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written and reviewed by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
Last reviewed September 2026 · checked against the official PMI exam blueprint
This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.