Courseiva

CAPM Practice Question: Project Management Fundamentals and Core Concepts

Which of the following best describes a project versus ongoing operations?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Projects are temporary; operations are ongoing

Projects are temporary endeavors with a defined beginning and end, whereas operations are ongoing activities that produce repetitive outputs. Option A is incorrect because projects deliver unique outputs, not ongoing outputs. Option B is incorrect because projects are unique, not repetitive, and operations are repetitive. Option C is incorrect because profitability is not a defining characteristic; both projects and operations can aim for profit or value.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Projects have ongoing outputs; operations have defined deliverables

    Why it's wrong here

    Operations have ongoing outputs.

  • Projects are repetitive; operations are unique

    Why it's wrong here

    Projects are unique, operations are repetitive.

  • Projects focus on profit; operations focus on value

    Why it's wrong here

    Both can focus on value.

  • Projects are temporary; operations are ongoing

    Why this is correct

    This is the defining characteristic.

About these practice questions

This CAPM question is part of Courseiva's 487-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more way this is tested on CAPM

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. Which of the following best defines a project?

easy
  • A.An ongoing process to produce the same product repeatedly.
  • B.A set of tasks that can be completed in any order.
  • C.A temporary endeavor undertaken to create a unique product, service, or result.
  • D.A routine operation with a defined start and end.

Why C: The Project Management Institute (PMI) defines a project as 'a temporary endeavor undertaken to create a unique product, service, or result.' The key characteristics are temporality (definite start and end) and uniqueness (the output is different from all other products or services). This definition is foundational to the CAPM exam and distinguishes projects from operations.

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.