CAPM · topic practice

Project Management Fundamentals and Core Concepts practice questions

Practise Certified Associate in Project Management CAPM Project Management Fundamentals and Core Concepts practice questions — original exam-style scenarios with answer choices, explanations, and analysis of common mistakes.

Courseiva uses original exam-style practice questions designed for learning and revision. The goal is to understand the concepts, recognise exam patterns, and improve through explanations — not memorise copied exam dumps.

Reviewed byJohnson Ajibi· MSc IT Security
20 questionsDomain: Project Management Fundamentals and Core Concepts

What the exam tests

What to know about Project Management Fundamentals and Core Concepts

Project Management Fundamentals and Core Concepts questions test whether you can apply the concept in context, not just recognise a definition.

How the topic appears in realistic exam-style scenarios.

Which detail in the question changes the correct answer.

How to eliminate plausible but wrong options.

How to connect the question back to the wider exam objective.

Watch out for

Common Project Management Fundamentals and Core Concepts exam traps

  • Answering from memory before reading the full scenario.
  • Missing a constraint such as cost, availability, security, scope or command context.
  • Choosing a broad answer when the question asks for the most specific fix.
  • Ignoring why the wrong options are tempting.

Practice set

Project Management Fundamentals and Core Concepts questions

20 questions · select your answer, then reveal the explanation

A project manager is reviewing the project charter and notices that the business case includes a cost-benefit analysis with a Net Present Value (NPV) of $50,000 and an Internal Rate of Return (IRR) of 12%. The company's required rate of return is 10%. What should the project manager conclude about this project?

During project execution, a key stakeholder requests a significant change that will increase project scope. The project manager performs an impact analysis and determines that the change will delay the project by two weeks and increase costs by 10%. However, the change is critical for regulatory compliance. What should the project manager do first?

A project manager is estimating the duration of an activity. The optimistic estimate is 4 days, the pessimistic is 12 days, and the most likely is 6 days. Using the PERT three-point estimate, what is the expected duration?

Question 4mediummultiple choice
Read the full NAT/PAT explanation →

A project team is working on a software development project. The project manager notices that the team is spending too much time on unplanned work, resulting in delays to the critical path. What technique should the project manager use to reduce unplanned work and improve focus?

A project manager is assigned to a project that is in the planning phase. The sponsor asks the project manager to include a 10% contingency reserve in the budget. The project manager knows that the project has a high degree of uncertainty. What should the project manager do?

Which TWO of the following are outputs of the Identify Stakeholders process?

Which THREE of the following are types of dependencies that can exist between project activities?

A project manager is leading a software development project. The sponsor has requested a new feature that was not part of the original scope. The project manager assesses that adding this feature will require additional resources and will extend the timeline by two weeks. What should the project manager do first?

A project team is working on a construction project. The project manager notices that the actual cost is consistently higher than planned. Which project management process is most directly responsible for monitoring and controlling costs?

A project manager is assigned to a project that is in execution phase. The project has a cost performance index (CPI) of 0.8 and a schedule performance index (SPI) of 1.1. Which of the following best describes the current status of the project?

Refer to the exhibit. What is the total float of Task B?

Exhibit

Refer to the exhibit.

Task A: duration 5 days, predecessor: none
Task B: duration 3 days, predecessor: A
Task C: duration 4 days, predecessor: A
Task D: duration 2 days, predecessor: B, C

During project planning, the project manager wants to ensure that all work required to complete the project is identified. Which document is the primary output of the process that defines and controls what is included in the project?

Which TWO of the following are outputs of the Identify Risks process?

Which THREE of the following are components of the project charter?

A project team is experiencing frequent changes in requirements. The project manager wants to minimize disruptions. Which approach is best to manage changes effectively?

A project manager is leading a software development project. During the planning phase, the team identifies a significant risk that a key third-party API may be deprecated before the project completes. The project sponsor asks for a risk response strategy. Which strategy should the project manager recommend to best address this risk?

A project team is struggling with unclear roles and responsibilities, leading to duplicated work and missed tasks. Which document should the project manager create or update to resolve this issue?

During project execution, a key stakeholder requests a change that would add a new feature. The project manager assesses the impact and finds that it will increase the project cost by 15% and extend the schedule by three weeks. The sponsor is concerned about the budget but sees the value. What should the project manager do next?

Which TWO of the following are examples of project constraints? (Choose two.)

Question 20hardmultiple choice
Read the full NAT/PAT explanation →

You are a project manager for a construction project to build a new office wing. The project is in the execution phase. The team reports that the foundation work is behind schedule because of unexpected soil conditions that require additional stabilization. The project plan had a contingency reserve for such issues. The project sponsor is concerned about the delay and asks you to compress the schedule to recover. The project has a fixed completion date and cannot be delayed. After analyzing the schedule, you find that there is float on some non-critical paths, but critical path activities are already resource-loaded. What is the BEST course of action to address the delay while keeping the project on track?

Free account

Track your progress over time

Create a free account to save your results and see which topics improve across sessions.

Focused Project Management Fundamentals and Core Concepts sessions

Start a Project Management Fundamentals and Core Concepts only practice session

Every question in these sessions is drawn from the Project Management Fundamentals and Core Concepts domain — nothing else.

Related practice questions

Related CAPM topic practice pages

Move into related areas when this topic feels solid.

Frequently asked questions

What does the CAPM exam test about Project Management Fundamentals and Core Concepts?
Project Management Fundamentals and Core Concepts questions test whether you can apply the concept in context, not just recognise a definition.
How should I use these practice questions?
Select your answer before revealing the explanation. Then read why each option is right or wrong — this active recall approach builds retention far faster than re-reading notes.
Can I practise just Project Management Fundamentals and Core Concepts questions in a focused session?
Yes — the session launcher on this page draws every question from the Project Management Fundamentals and Core Concepts domain. Use a 10-question session first to gauge your baseline, then move to 20 or 30 once the weak spots are clear.
Where can I practise other CAPM topics?
Use the topic links above to move to related areas, or go back to the CAPM question bank to see all topics.
Are these real exam questions or dumps?
These are original practice questions written to test the same concepts the CAPM exam covers. They are not copied from any real exam or dump site.