Courseiva

CAPM · topic practice

Project Management Fundamentals and Core Concepts practice questions

This domain covers the foundational vocabulary and mechanics of managing projects: distinguishing projects from operations, applying the PMBOK process groups and knowledge areas, identifying constraints, and handling change through integrated control. CAPM questions here are scenario-based, asking you to classify situations, pick appropriate documents, and choose the correct next action rather than recall isolated definitions.

Courseiva uses original exam-style practice questions designed for learning and revision. The goal is to understand the concepts, recognise exam patterns, and improve through explanations — not memorise copied exam dumps.

Editorial oversight:Johnson Ajibi· MSc IT Security, IEEE Senior Member
20 questionsDomain: Project Management Fundamentals and Core Concepts

What the exam tests

What to know about Project Management Fundamentals and Core Concepts

You must be able to classify work as project or operations, name the process groups and constraints, and choose the correct next step when a change appears. The single most important thing: never act on a change before evaluating its impact and routing it through the change control process.

Distinguishing a temporary, unique project from repetitive ongoing operations

Identifying the triple constraint and competing project constraints like scope, schedule, cost, quality, and risk

Applying the five process groups: initiating, planning, executing, monitoring and controlling, closing

Using the change control process to evaluate and route scope change requests through the change control board

Watch out for

Common Project Management Fundamentals and Core Concepts exam traps

  • ▸Treating operations as projects, or assuming a project continues indefinitely once the product is delivered and supported.
  • ▸Approving or implementing a stakeholder change request before assessing impact and following the change management plan.
  • ▸Confusing project constraints with assumptions, or listing only cost and time while ignoring scope, quality, and risk.

Practice set

Project Management Fundamentals and Core Concepts questions

20 questions · select your answer, then reveal the explanation

Which TWO of the following are outputs of the Identify Stakeholders process?

Which THREE of the following are types of dependencies that can exist between project activities?

During project planning, the project manager wants to ensure that all work required to complete the project is identified. Which document is the primary output of the process that defines and controls what is included in the project?

A project manager is leading a software development project. During the planning phase, the team identifies a significant risk that a key third-party API may be deprecated before the project completes. The project sponsor asks for a risk response strategy. Which strategy should the project manager recommend to best address this risk?

You are a project manager for a construction project to build a new office wing. The project is in the execution phase. The team reports that the foundation work is behind schedule because of unexpected soil conditions that require additional stabilization. The project plan had a contingency reserve for such issues. The project sponsor is concerned about the delay and asks you to compress the schedule to recover. The project has a fixed completion date and cannot be delayed. After analyzing the schedule, you find that there is float on some non-critical paths, but critical path activities are already resource-loaded. What is the BEST course of action to address the delay while keeping the project on track?

A project manager is assigned to a new product development project. The project charter has been approved, and the team is preparing the project management plan. During the planning process, the project manager wants to ensure that all project work is aligned with the business objectives. Which document should the project manager review to confirm the alignment of the project with organizational strategy?

Refer to the exhibit. The project manager notices that the resource histogram shows a peak of 15 FTEs in Week 2, exceeding the available 12 FTEs. The project manager needs to bring the resource usage within the limit without increasing the project duration or budget. Which action should the project manager take?

Exhibit

Refer to the exhibit.

Resource Histogram:

Week 1: 10 FTEs
Week 2: 15 FTEs
Week 3: 12 FTEs
Week 4: 8 FTEs

Total available FTEs per week: 12

Cost per FTE: $1000/week

Project budget: $50,000

A project manager is leading a software development project. The team has completed the first iteration and is reviewing the lessons learned. Which output of the Manage Project Knowledge process should the project manager update with the lessons learned from this iteration?

Drag and drop the steps for developing a project schedule in the correct order.

Drag or tap steps into the slots.

Steps
Order
1Step 1
2Step 2
3Step 3
4Step 4
5Step 5

Match each project document to its description.

Drag a concept onto its matching description — or click a concept then click the description.

Concepts
Matches

Authorizes the project and assigns PM

Comprehensive plan for execution

Hierarchical decomposition of work

List of identified risks and responses

Documents and tracks project issues

Match each project role to its responsibility.

Drag a concept onto its matching description — or click a concept then click the description.

Concepts
Matches

Leads project team and manages constraints

Provides resources and champions project

Defines product backlog and priorities

Facilitates Scrum process and removes impediments

Elicits and documents requirements

Which of the following best defines a project?

Which TWO of the following are project management process groups?

Refer to the exhibit. Based on the probability and impact values, which risk has the highest risk score?

Exhibit

{
  "risks": [
    {"id": "R1", "probability": 0.3, "impact": 0.5},
    {"id": "R2", "probability": 0.8, "impact": 0.2},
    {"id": "R3", "probability": 0.6, "impact": 0.9},
    {"id": "R4", "probability": 0.4, "impact": 0.7}
  ]
}

Refer to the exhibit. How many work packages are at the lowest level of the WBS?

Exhibit

{
  "wbs": {
    "id": "1.0",
    "name": "Project",
    "children": [
      {"id": "1.1", "name": "Planning", "level": 2},
      {"id": "1.2", "name": "Execution", "level": 2, "children": [
        {"id": "1.2.1", "name": "Develop", "level": 3},
        {"id": "1.2.2", "name": "Test", "level": 3}
      ]},
      {"id": "1.3", "name": "Close", "level": 2}
    ]
  }
}

Refer to the exhibit. The project manager is reviewing deployment logs. Which statement best describes the event?

Exhibit

Exhibit:
```
[2025-04-01 10:15:32] ERROR: Connection timeout to database 'sales_db' during query execution. Retry 1 of 3.
[2025-04-01 10:15:35] INFO: Retry successful.
```

Refer to the exhibit. The project manager needs to calculate the total hours assigned to each resource. Which resource has the highest total assigned hours?

Exhibit

Exhibit:
```json
{
  "ResourceAssignments": [
    {"Resource": "Alice", "Task": "Design", "Hours": 40},
    {"Resource": "Bob", "Task": "Development", "Hours": 80},
    {"Resource": "Charlie", "Task": "Testing", "Hours": 30},
    {"Resource": "Alice", "Task": "Documentation", "Hours": 20}
  ]
}
```

Refer to the exhibit. Which task has a dependency that requires the successor to start 2 days after the predecessor starts?

Exhibit

Exhibit:
```
Task dependencies from project scheduling tool:
Task A - Start-to-Start with 2 days lag (SS+2d)
Task B - Finish-to-Finish with 3 days lead (FF-3d)
Task C - Finish-to-Start (FS)
Task D - Start-to-Start (SS)
```

A project manager is estimating activity durations. The team provides three estimates: optimistic 10 days, pessimistic 20 days, most likely 14 days. Using the PERT beta distribution, what is the expected duration?

Refer to the exhibit. What is the cost performance index (CPI)?

Exhibit

{
  "EV": 5000,
  "AC": 6000,
  "PV": 5500
}

Free account

Track your progress over time

Create a free account to save your results and see which topics improve across sessions.

Focused Project Management Fundamentals and Core Concepts sessions

Start a Project Management Fundamentals and Core Concepts only practice session

Every question in these sessions is drawn from the Project Management Fundamentals and Core Concepts domain — nothing else.

Related practice questions

Related CAPM topic practice pages

Move into related areas when this topic feels solid.

Frequently asked questions

What does the CAPM exam test about Project Management Fundamentals and Core Concepts?
You must be able to classify work as project or operations, name the process groups and constraints, and choose the correct next step when a change appears. The single most important thing: never act on a change before evaluating its impact and routing it through the change control process.
How should I use these practice questions?
Select your answer before revealing the explanation. Then read why each option is right or wrong — this active recall approach builds retention far faster than re-reading notes.
Can I practise just Project Management Fundamentals and Core Concepts questions in a focused session?
Yes — the session launcher on this page draws every question from the Project Management Fundamentals and Core Concepts domain. Use a 10-question session first to gauge your baseline, then move to 20 or 30 once the weak spots are clear.
Where can I practise other CAPM topics?
Use the topic links above to move to related areas, or go back to the CAPM question bank to see all topics.
Are these real exam questions or dumps?
These are original practice questions written to test the same concepts the CAPM exam covers. They are not copied from any real exam or dump site.