Courseiva

CAPM Practice Question: Project Management Fundamentals and Core Concepts

During project planning, the team identifies that the project requires a specific vendor for a critical component. Which process group is being executed?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Planning

Identifying procurement needs, such as requiring a specific vendor, is part of the Planning process group. Initiating focuses on project authorization, Executing on performing the work, and Closing on finalizing project activities.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Initiating

    Why it's wrong here

    Initiating involves authorizing the project or phase, not detailed procurement planning.

  • Closing

    Why it's wrong here

    Closing finalizes contracts and project, not initial vendor identification.

  • Executing

    Why it's wrong here

    Executing implements plans; procurement decisions are planned earlier.

  • Planning

    Why this is correct

    Procurement planning is a Planning process.

About these practice questions

Courseiva writes every CAPM question from scratch — 487 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.