CAPM Agile Frameworks and Methodologies Practice Question

A company transitioning from a waterfall to a Scrum framework wants to ensure continuous improvement. Which Scrum event is specifically designed for inspecting and adapting the process?

⚠ Common exam trap

CAPM often tests whether candidates confuse the Sprint Retrospective with the Sprint Review, or incorrectly select the Daily Scrum as the process improvement event.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Sprint Retrospective

The Sprint Retrospective is the Scrum event specifically designed for inspecting and adapting the process. It occurs at the end of each Sprint and focuses on how the team worked together, identifying improvements to apply in the next Sprint. The Daily Scrum is for daily coordination, the Sprint Review is for inspecting the product increment, and Sprint Planning is for planning the upcoming Sprint's work.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Daily Scrum

    Why it's wrong here

    The Daily Scrum inspects progress toward the Sprint Goal and adapts the plan for the next 24 hours, not the team's process. It suits daily synchronisation and impediment surfacing; continuous process improvement is the Retrospective's purpose.

  • ✗

    Sprint Review

    Why it's wrong here

    The Sprint Review inspects the increment with stakeholders and adapts the Product Backlog; it does not examine how the team works. It is the right event for gathering feedback on delivered value, whereas process inspection belongs to the Retrospective.

  • ✓

    Sprint Retrospective

    Why this is correct

    The Sprint Retrospective is the only Scrum event whose explicit purpose is inspecting how the team worked and adapting its process, satisfying the continuous-improvement constraint. Unlike the Daily Scrum, which inspects progress toward the Sprint Goal, it focuses on people, interactions, tools and Definition of Done, producing actionable improvements for the next Sprint.

  • ✗

    Sprint Planning

    Why it's wrong here

    Sprint Planning inspects the Product Backlog and adapts the Sprint Backlog and goal; it defines the work, not the process. It is correct when scoping an upcoming Sprint, while inspecting and adapting how the team works is the Retrospective's remit.

About these practice questions

Courseiva writes every CAPM question from scratch — 451 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PMI exam blueprint

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.