Courseiva

CAPM Practice Question: Project Management Fundamentals and Core Concepts

A project is behind schedule. Which schedule compression technique involves adding additional resources to critical path activities?

⚠ Common exam trap

CAPM often tests the confusion between crashing and fast-tracking; candidates must remember crashing adds resources to critical path activities, while fast-tracking overlaps activities and increases risk.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Crashing

Crashing is the schedule compression technique that adds additional resources to critical path activities to shorten duration, typically at increased cost. It is used when the project must be accelerated and cost is acceptable. Resource leveling, by contrast, adjusts start/finish dates based on resource constraints and often extends duration.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Resource leveling

    Why it's wrong here

    Resource leveling resolves over-allocation by delaying tasks within their float, which typically extends duration and cannot compress a late schedule. It is tempting because it also manipulates resourcing, but its purpose is smoothing demand, not shortening the critical path by adding people.

  • ✗

    Monte Carlo simulation

    Why it's wrong here

    Monte Carlo simulation models schedule risk probabilistically by running many iterations; it never adds resources. It is tempting because it quantifies schedule uncertainty and completion-date confidence, which is its actual purpose, but the stem demands crashing — extra resources on critical path activities.

  • ✗

    Rolling wave planning

    Why it's wrong here

    Rolling wave planning progressively elaborates work as details emerge; it does not add resources. Adding resources to critical path activities is crashing, so rolling wave planning is tempting as a scheduling technique but addresses uncertainty, not duration compression.

  • ✓

    Crashing

    Why this is correct

    Crashing shortens the critical path by adding resources, such as extra staff or overtime, to critical activities. It trades increased cost for reduced duration, directly addressing the behind-schedule constraint where activities sit on the critical path.

About these practice questions

Courseiva writes every CAPM question from scratch — 451 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PMI exam blueprint

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.