CAPM Predictive Plan-Based Methodologies Practice Question
In a predictive project, the project manager wants to ensure that the project team understands their roles and responsibilities. Which document is used to define roles and responsibilities?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Responsibility assignment matrix (RAM)
The Responsibility Assignment Matrix (RAM) is used to define roles and responsibilities. Option A is correct.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Responsibility assignment matrix (RAM)
Why this is correct
RAM commonly shows roles and responsibilities.
- ✗
Work breakdown structure (WBS)
Why it's wrong here
WBS shows deliverables.
- ✗
Resource breakdown structure (RBS)
Why it's wrong here
RBS shows resource categories.
- ✗
Organizational breakdown structure (OBS)
Why it's wrong here
OBS shows organizational units.
Go deeper
Related to this question
About these practice questions
This CAPM question is part of Courseiva's 487-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.