Courseiva
Question 204 of 487
Predictive Plan-Based MethodologiesmediumMultiple ChoiceObjective-mapped

CAPM Predictive Plan-Based Methodologies Practice Question

A project manager is developing a work breakdown structure (WBS) for a software development project. The team is struggling with defining the lowest-level work packages. Which technique should the project manager use to ensure the WBS is complete and properly decomposed?

⚠ Common exam trap

Many candidates confuse decomposition with rolling wave planning, thinking that progressive elaboration is the same as breaking down the WBS, but decomposition is a distinct, structured technique applied upfront to create a complete WBS, not a phased planning approach.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Decomposition

Decomposition is the correct technique because it is the process of subdividing project deliverables into smaller, more manageable components until the work package level is reached. This directly addresses the team's struggle with defining the lowest-level work packages, ensuring the WBS is complete and properly decomposed by breaking down deliverables iteratively.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Decomposition

    Why this is correct

    Decomposition is the technique that subdivides deliverables into work packages.

  • Critical path method

    Why it's wrong here

    Critical path method is a schedule analysis technique, not related to WBS decomposition.

  • Expert judgment

    Why it's wrong here

    Expert judgment is a tool used during decomposition, but the technique itself is decomposition.

  • Rolling wave planning

    Why it's wrong here

    Rolling wave planning is a form of progressive elaboration, not the technique for initially decomposing the WBS.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 11, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.