- A
Apply crashing to the critical path activities.
Why wrong: Crashing adds resources to speed up, but doesn't reduce unplanned work.
- B
Perform resource leveling to smooth resource usage.
Why wrong: Resource leveling may delay the project, not reduce unplanned work.
- C
Use fast tracking to overlap activities.
Why wrong: Fast tracking may increase rework and unplanned work.
- D
Implement critical chain project management.
Critical chain focuses on resource constraints and buffers, reducing unplanned work.
Quick Answer
The correct answer is to implement critical chain project management. This technique is specifically designed to reduce unplanned work by inserting strategic buffers—such as a project buffer at the end and feeding buffers at integration points—which absorb delays and protect the critical path from disruptions. By enforcing a "relay race" work ethic where team members focus on one task at a time and pass work forward without multitasking, CCPM directly addresses the root cause of unplanned work eating into schedule reserves. On the CAPM exam, this question tests your understanding of how CCPM differs from traditional critical path method; a common trap is confusing it with simply adding more resources or crashing the schedule. Remember the memory tip: "Buffers beat burnout"—the buffers in CCPM are not slack but deliberate shields against the chaos of unplanned tasks, keeping the team focused on priority order.
CAPM Practice Question: Project Management Fundamentals and Core Concepts
This CAPM practice question tests your understanding of project management fundamentals and core concepts. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
A project team is working on a software development project. The project manager notices that the team is spending too much time on unplanned work, resulting in delays to the critical path. What technique should the project manager use to reduce unplanned work and improve focus?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Implement critical chain project management.
Critical chain project management (CCPM) is specifically designed to protect the critical path from disruptions like unplanned work by inserting buffers (e.g., feeding buffers, project buffer) and enforcing a 'relay race' work ethic. This technique reduces multitasking and focuses the team on completing tasks in priority order, directly addressing the root cause of delays from unplanned work.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Apply crashing to the critical path activities.
Why it's wrong here
Crashing adds resources to speed up, but doesn't reduce unplanned work.
- ✗
Perform resource leveling to smooth resource usage.
Why it's wrong here
Resource leveling may delay the project, not reduce unplanned work.
- ✗
Use fast tracking to overlap activities.
Why it's wrong here
Fast tracking may increase rework and unplanned work.
- ✓
Implement critical chain project management.
Why this is correct
Critical chain focuses on resource constraints and buffers, reducing unplanned work.
Related concept
Read the scenario before looking for a memorised answer.
Common exam traps
Common exam trap: answer the scenario, not the keyword
The trap here is that candidates confuse schedule compression techniques (crashing, fast tracking) with schedule protection techniques, failing to recognize that unplanned work requires a buffer-based approach like CCPM rather than simply accelerating planned activities.
Detailed technical explanation
How to think about this question
CCPM uses a 'buffer management' mechanism where the project buffer (typically 50% of the critical path duration) absorbs delays from unplanned work, and feeding buffers protect the critical path from non-critical chain delays. In practice, CCPM enforces a 'no multitasking' rule by prioritizing tasks based on buffer penetration, which directly reduces the time lost to context switching and unplanned interruptions. A real-world scenario is a software team using CCPM to shield the critical path from urgent bug fixes by allocating a 'buffer' for such unplanned work, ensuring the core feature delivery stays on track.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
TExam Day Tips
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A small business has 20 workstations on the 192.168.1.0/24 network and one public IP from its ISP. The router uses PAT (NAT overload) so all 20 devices share one public address using different source ports. NAT questions test whether you understand the four address terms and which direction each translation applies.
What to study next
Got this wrong? Here's your next step.
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
- →
Project Management Fundamentals and Core Concepts — study guide chapter
Learn the concepts, then practise the questions
- →
Project Management Fundamentals and Core Concepts practice questions
Targeted practice on this topic area only
- →
All CAPM questions
503 questions across all exam domains
- →
Certified Associate in Project Management CAPM study guide
Full concept coverage aligned to exam objectives
- →
CAPM practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related CAPM practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
Agile Frameworks and Methodologies practice questions
Practise CAPM questions linked to Agile Frameworks and Methodologies.
Project Management Fundamentals and Core Concepts practice questions
Practise CAPM questions linked to Project Management Fundamentals and Core Concepts.
Predictive Plan-Based Methodologies practice questions
Practise CAPM questions linked to Predictive Plan-Based Methodologies.
Business Analysis Frameworks practice questions
Practise CAPM questions linked to Business Analysis Frameworks.
CAPM fundamentals practice questions
Practise CAPM questions linked to CAPM fundamentals.
CAPM scenario practice questions
Practise CAPM questions linked to CAPM scenario.
CAPM troubleshooting practice questions
Practise CAPM questions linked to CAPM troubleshooting.
Practice this exam
Start a free CAPM practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this CAPM question test?
Project Management Fundamentals and Core Concepts — This question tests Project Management Fundamentals and Core Concepts — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Implement critical chain project management. — Critical chain project management (CCPM) is specifically designed to protect the critical path from disruptions like unplanned work by inserting buffers (e.g., feeding buffers, project buffer) and enforcing a 'relay race' work ethic. This technique reduces multitasking and focuses the team on completing tasks in priority order, directly addressing the root cause of delays from unplanned work.
What should I do if I get this CAPM question wrong?
Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Keep practising
More CAPM practice questions
- Which THREE factors should a business analyst consider when selecting an elicitation technique for a project?
- Drag and drop the steps for conducting a procurement process in the correct order.
- Drag and drop the steps for controlling project changes according to the integrated change control process.
- Drag and drop the steps for managing project quality in the correct order.
- Drag and drop the steps for closing a project phase or project in the correct order.
- Drag and drop the steps for managing project communications in the correct order.
Last reviewed: Jun 11, 2026
This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.