A BA is conducting stakeholder analysis and needs to categorize stakeholders based on their influence and interest. Which grid is commonly used?

⚠ Common exam trap

The trap is confusing the power/interest grid with other stakeholder tools like the RACI matrix or communication matrix; candidates may pick RACI because it also involves stakeholders, but it serves a different purpose.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Power/interest grid

The power/interest grid is a stakeholder analysis tool that categorizes stakeholders based on their level of authority (power) and concern (interest) in the project. It helps determine engagement strategies, such as managing closely those with high power and high interest. This grid is commonly used in business analysis and project management to prioritize stakeholder communication.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Communication matrix

    Why it's wrong here

    A communication matrix documents who receives which information, at what frequency and through which channel; it does not plot stakeholders against influence and interest. It is tempting because both artefacts support engagement planning, but the power/interest grid is the tool that categorises stakeholders on those two axes.

  • ✗

    Decision tree

    Why it's wrong here

    A decision tree models branching choices and their expected outcomes under uncertainty; it has no influence or interest axes. It is tempting because both are analysis techniques used during planning, but stakeholder categorisation requires the power/interest grid, which maps each stakeholder's authority against their concern.

  • ✗

    RACI matrix

    Why it's wrong here

    A RACI matrix assigns responsibility, accountability, consultation and information roles for tasks or deliverables; it does not position stakeholders by influence and interest. It is tempting because RACI also clarifies stakeholder involvement, but the power/interest grid is the artefact that categorises them on those two dimensions.

  • ✓

    Power/interest grid

    Why this is correct

    The power/interest grid plots stakeholders by authority over the project and their level of concern, producing tailored engagement strategies for each quadrant. It directly satisfies the stem's requirement to categorise stakeholders by influence and interest.

About these practice questions

Courseiva writes every CAPM question from scratch — 451 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PMI exam blueprint

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.