A project manager is performing risk identification. Which two inputs are essential for this process? (Choose two)

⚠ Common exam trap

CAPM often tests the distinction between inputs and outputs of risk management processes, and candidates frequently confuse the Risk register as an input to Identify Risks when it is actually an output that gets updated.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Stakeholder register

The Stakeholder register (A) is a correct input because it identifies the people and organizations who may be affected by or can influence project risks, providing their roles, interests, and communication needs that feed directly into risk identification. The Risk management plan (D) is also correct because it defines the risk methodology, roles and responsibilities, budget and schedule for risk activities, risk categories, and stakeholder risk appetite, all of which guide how risk identification is performed. Work performance reports (B) are not an input to Identify Risks; they are outputs of Monitor and Control Project Work used in other processes such as Monitor Risks. The Change log (C) is not an input to Identify Risks; it is used in processes like Control Quality and Monitor Risks. The Risk register (E) is an output of Identify Risks, not an input, though it becomes an input to later risk processes.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Stakeholder register

    Why this is correct

    The stakeholder register identifies everyone with an interest in the project, supplying the perspectives needed to surface risks during identification. It satisfies the input requirement by revealing external and internal parties whose objectives, concerns or influence may generate project threats and opportunities.

  • ✗

    Work performance reports

    Why it's wrong here

    Work performance reports are used during monitoring, not identification.

  • ✗

    Change log

    Why it's wrong here

    The change log may be a project document input, but it is not essential; the risk management plan and stakeholder register are more critical.

  • ✓

    Risk management plan

    Why this is correct

    The risk management plan supplies the tailored framework for risk identification: it defines the methodology, roles, budget and timing, and the risk categories and probability-impact scales the team must apply. Without it, identification lacks the agreed structure the process requires as its essential input.

  • ✗

    Risk register

    Why it's wrong here

    The risk register is an output of risk identification, not an input.

About these practice questions

This CAPM question is part of Courseiva's 451-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PMI exam blueprint

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.