CAPM Practice Question: Project Management Fundamentals and Core Concepts
Which THREE are components of the project management plan?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Cost baseline
The cost baseline (B), scope baseline (D), and schedule baseline (E) are components of the project management plan. The risk register (A) and stakeholder register (C) are project documents, not part of the plan.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✗
Risk register
Why it's wrong here
A project document, not part of the project management plan.
- ✓
Cost baseline
Why this is correct
Part of the project management plan, defines the budget.
- ✗
Stakeholder register
Why it's wrong here
A project document, not part of the project management plan.
- ✓
Scope baseline
Why this is correct
Part of the project management plan, defines the scope.
- ✓
Schedule baseline
Why this is correct
Part of the project management plan, defines the schedule.
Go deeper
Related to this question
About these practice questions
Courseiva writes every CAPM question from scratch — 487 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.