Courseiva

CAPM Practice Question: Project Management Fundamentals and Core Concepts

Which THREE are components of the project management plan?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Cost baseline

The cost baseline (B), scope baseline (D), and schedule baseline (E) are components of the project management plan. The risk register (A) and stakeholder register (C) are project documents, not part of the plan.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Risk register

    Why it's wrong here

    A project document, not part of the project management plan.

  • Cost baseline

    Why this is correct

    Part of the project management plan, defines the budget.

  • Stakeholder register

    Why it's wrong here

    A project document, not part of the project management plan.

  • Scope baseline

    Why this is correct

    Part of the project management plan, defines the scope.

  • Schedule baseline

    Why this is correct

    Part of the project management plan, defines the schedule.

About these practice questions

Courseiva writes every CAPM question from scratch — 487 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.