CAPM Predictive Plan-Based Methodologies Practice Question

Drag and drop the steps for controlling project changes according to the integrated change control process.

Drag steps to the numbered slots on the right, or tap a step then tap a slot.

Steps
Order
1Step 1
2Step 2
3Step 3
4Step 4
5Step 5

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Step 1: Submit change request; Step 2: Review change request; Step 3: Approve or reject change; Step 4: Update project management plan and communicate outcome.

Change control involves submitting, reviewing, deciding, updating plans, and communicating outcomes.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Step 1: Submit change request; Step 2: Review change request; Step 3: Approve or reject change; Step 4: Update project management plan and communicate outcome.

    Why this is correct

    This is correct because integrated change control begins with submission of a change request, followed by impact review, a decision (approval/rejection), and finally updating relevant documents and communicating the outcome.

  • Step 1: Review change request; Step 2: Submit change request; Step 3: Approve or reject change; Step 4: Update project management plan and communicate outcome.

    Why it's wrong here

    This is incorrect because reviewing a change request before it has been submitted is not possible; submission must occur first.

  • Step 1: Submit change request; Step 2: Approve or reject change; Step 3: Review change request; Step 4: Update project management plan and communicate outcome.

    Why it's wrong here

    This is incorrect because a decision on the change cannot be made before reviewing its impact; the review must precede the approve/reject step.

  • Step 1: Submit change request; Step 2: Review change request; Step 3: Update project management plan and communicate outcome; Step 4: Approve or reject change.

    Why it's wrong here

    This is incorrect because updating plans and communicating outcomes must occur after the decision, not before; the decision is a prerequisite for updates.

About these practice questions

Courseiva writes every CAPM question from scratch — 487 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.