Drag steps to the numbered slots on the right, or tap a step then tap a slot.
CAPM Predictive Plan-Based Methodologies Practice Question
Drag and drop the steps for controlling project changes according to the integrated change control process.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Step 1: Submit change request; Step 2: Review change request; Step 3: Approve or reject change; Step 4: Update project management plan and communicate outcome.
Change control involves submitting, reviewing, deciding, updating plans, and communicating outcomes.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Step 1: Submit change request; Step 2: Review change request; Step 3: Approve or reject change; Step 4: Update project management plan and communicate outcome.
Why this is correct
This is correct because integrated change control begins with submission of a change request, followed by impact review, a decision (approval/rejection), and finally updating relevant documents and communicating the outcome.
- ✗
Step 1: Review change request; Step 2: Submit change request; Step 3: Approve or reject change; Step 4: Update project management plan and communicate outcome.
Why it's wrong here
This is incorrect because reviewing a change request before it has been submitted is not possible; submission must occur first.
- ✗
Step 1: Submit change request; Step 2: Approve or reject change; Step 3: Review change request; Step 4: Update project management plan and communicate outcome.
Why it's wrong here
This is incorrect because a decision on the change cannot be made before reviewing its impact; the review must precede the approve/reject step.
- ✗
Step 1: Submit change request; Step 2: Review change request; Step 3: Update project management plan and communicate outcome; Step 4: Approve or reject change.
Why it's wrong here
This is incorrect because updating plans and communicating outcomes must occur after the decision, not before; the decision is a prerequisite for updates.
Go deeper
Related to this question
About these practice questions
Courseiva writes every CAPM question from scratch — 487 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.