Courseiva

CAPM Predictive Plan-Based Methodologies Practice Question

Drag and drop the steps for controlling project changes according to the integrated change control process.

Drag or tap steps into the slots.

Steps
Order
1Step 1
2Step 2
3Step 3
4Step 4
5Step 5

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Step 1: Submit change request; Step 2: Review change request; Step 3: Approve or reject change; Step 4: Update project management plan and communicate outcome.

Change control involves submitting, reviewing, deciding, updating plans, and communicating outcomes.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Step 1: Submit change request; Step 2: Review change request; Step 3: Approve or reject change; Step 4: Update project management plan and communicate outcome.

    Why this is correct

    This is correct because integrated change control begins with submission of a change request, followed by impact review, a decision (approval/rejection), and finally updating relevant documents and communicating the outcome.

  • ✗

    Step 1: Review change request; Step 2: Submit change request; Step 3: Approve or reject change; Step 4: Update project management plan and communicate outcome.

    Why it's wrong here

    This is incorrect because reviewing a change request before it has been submitted is not possible; submission must occur first.

  • ✗

    Step 1: Submit change request; Step 2: Approve or reject change; Step 3: Review change request; Step 4: Update project management plan and communicate outcome.

    Why it's wrong here

    This is incorrect because a decision on the change cannot be made before reviewing its impact; the review must precede the approve/reject step.

  • ✗

    Step 1: Submit change request; Step 2: Review change request; Step 3: Update project management plan and communicate outcome; Step 4: Approve or reject change.

    Why it's wrong here

    This is incorrect because updating plans and communicating outcomes must occur after the decision, not before; the decision is a prerequisite for updates.

About these practice questions

Courseiva writes every CAPM question from scratch — 451 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.