Courseiva
Question 167 of 487
Project Management Fundamentals and Core ConceptsmediumMultiple ChoiceObjective-mapped

CAPM Practice Question: Project Management Fundamentals and Core Concepts

During project execution, a key stakeholder requests a change that would add a new feature to the product. The project manager evaluates the impact on scope, schedule, and cost. According to the change management plan, which step should the project manager take first?

⚠ Common exam trap

The trap here is that candidates often jump to 'submit to CCB' (Option B) because they know changes need approval, but they forget that the impact analysis must be completed first to provide the CCB with the necessary information for decision-making.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Analyze the impact of the change on the project constraints

The change management plan requires the project manager to first analyze the impact of the proposed change on scope, schedule, and cost before any further action. This analysis provides the necessary data to determine whether the change should be submitted to the CCB for approval. Skipping this step would violate the defined change control process.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Analyze the impact of the change on the project constraints

    Why this is correct

    Impact analysis is the first step to understand the effects of the change.

  • Submit the change request to the change control board (CCB) for approval

    Why it's wrong here

    The impact must be assessed before submitting to CCB.

  • Implement the change and document it later

    Why it's wrong here

    Changes must follow the change control process and be approved before implementation.

  • Reject the change because it was not part of the original scope

    Why it's wrong here

    Changes should be evaluated through the formal process, not automatically rejected.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Last reviewed: Jun 11, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.