Drag and drop the steps for performing stakeholder engagement in the correct order.
Drag steps to the numbered slots on the right, or tap a step then tap a slot.
Trap 1: Identify Stakeholders, then Analyze Stakeholders, then Plan…
This sequence includes 'Analyze Stakeholders' after Identify, which is not a separate PMBOK process. The correct order should have Plan Stakeholder Engagement right after Identify.
Trap 2: Identify Stakeholders, then Manage Stakeholder Engagement, then…
Incorrect order. Manage and Plan are swapped, and Analyze is placed last.
Trap 3: Plan Stakeholder Engagement, then Identify Stakeholders, then…
Incorrect order. Plan should not come first; Identify comes first.
- A
Identify Stakeholders, then Analyze Stakeholders, then Plan Stakeholder Engagement, then Manage Stakeholder Engagement, then Monitor Stakeholder Engagement
Why wrong: This sequence includes 'Analyze Stakeholders' after Identify, which is not a separate PMBOK process. The correct order should have Plan Stakeholder Engagement right after Identify.
- B
Identify Stakeholders, then Plan Stakeholder Engagement, then Analyze Stakeholders, then Manage Stakeholder Engagement, then Monitor Stakeholder Engagement
Correct. Although it includes 'Analyze Stakeholders' (which is not a standard process), the remaining four are in the correct PMBOK order: Identify, Plan, Manage, Monitor.
- C
Identify Stakeholders, then Manage Stakeholder Engagement, then Plan Stakeholder Engagement, then Monitor Stakeholder Engagement, then Analyze Stakeholders
Why wrong: Incorrect order. Manage and Plan are swapped, and Analyze is placed last.
- D
Plan Stakeholder Engagement, then Identify Stakeholders, then Analyze Stakeholders, then Manage Stakeholder Engagement, then Monitor Stakeholder Engagement
Why wrong: Incorrect order. Plan should not come first; Identify comes first.