A project manager is performing qualitative risk analysis. Which TWO of the following are typical outputs of this process? (Select TWO)

⚠ Common exam trap

CAPM often tests the distinction between outputs of qualitative analysis and tools/techniques or outputs of other risk processes, causing candidates to select the probability and impact matrix as an output.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Risk register updates

Qualitative risk analysis produces updates to the risk register (option B), since the process records new information about each risk such as its probability, impact, urgency, and risk score, which are documented in the register. It also produces a list of prioritized risks (option D), because the primary purpose of qualitative analysis is to rank risks by their combined probability and impact so the team knows which ones to address first. Option A is incorrect because quantitative risk analysis results come from the separate Perform Quantitative Risk Analysis process, not the qualitative one. Option C is incorrect because risk responses are developed later in the Plan Risk Responses process. Option E is incorrect because the probability and impact matrix is a tool/technique used during qualitative risk analysis, not an output of it.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Quantitative risk analysis results

    Why it's wrong here

    Quantitative results, such as numerical probabilities of meeting cost and schedule targets, Monte Carlo simulation outputs and expected monetary values, come from Perform Quantitative Risk Analysis. That separate, optional process follows the qualitative one and usually looks only at the highest-priority risks. Qualitative analysis produces subjective ratings and a prioritised list, recorded in the risk register, which then determine whether quantitative analysis is worth doing.

  • ✓

    Risk register updates

    Why this is correct

    Perform Qualitative Risk Analysis records its findings in project documents, chiefly the risk register: probability and impact ratings, priority scores, risk owners, categories, urgency, and a watch list of low-priority risks. The risk report is also updated with an overview of the most significant risks. These updates feed every later risk process, from quantitative analysis to response planning, which is why register updates are a core output.

  • ✗

    Risk responses

    Why it's wrong here

    Risk responses are developed in Plan Risk Responses, which comes after the analysis processes: once risks are prioritised, the team chooses strategies such as avoid, transfer, mitigate, accept or escalate for threats, and exploit, share or enhance for opportunities. Qualitative analysis only rates and ranks risks, so responses cannot be one of its outputs. Remember the sequence: identify, analyse, plan responses, implement, monitor.

  • ✓

    List of prioritized risks

    Why this is correct

    Prioritised risk lists are a direct output of Perform Qualitative Risk Analysis, where each risk is rated by probability and impact to establish its relative ranking. This satisfies the process's purpose of ranking risks for subsequent quantitative analysis or response planning, as defined in the PMBOK Guide's data analysis and interpersonal techniques.

  • ✗

    Probability and impact matrix

    Why it's wrong here

    The probability and impact matrix is a tool used during qualitative analysis to turn ratings into priorities, with its scales and thresholds defined in the risk management plan. It is an input or technique rather than an output, so it does not answer the question. CAPM questions often test this exact distinction between inputs, tools and techniques, and outputs, so check which category an item belongs to.

About these practice questions

This CAPM question is part of Courseiva's 448-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

You might also like

Similar CAPM questions

Written and reviewed by Johnson Ajibi, MSc IT Security

Security Systems Architect · founder of Courseiva

Last reviewed September 2026 · checked against the official PMI exam blueprint

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.