Question 480 of 503
Predictive Plan-Based MethodologieseasyMultiple ChoiceObjective-mapped

Quick Answer

The answer is 16.67 days. This result comes from the PERT three-point estimate calculation, which uses the weighted average formula (Optimistic + 4×Most Likely + Pessimistic) / 6 to account for uncertainty in activity durations. By plugging in the given values—10 days optimistic, 15 days most likely, and 30 days pessimistic—you get (10 + 60 + 30) / 6 = 100 / 6, yielding 16.67 days. On the Certified Associate in Project Management CAPM exam, this question tests your ability to apply the beta distribution model for schedule estimation, a core concept in the Plan Schedule Management process. A common trap is mistakenly using a simple average (adding all three and dividing by three), which ignores the heavier weighting given to the most likely estimate. To avoid this, remember the mnemonic “O + 4M + P over 6” and that the “4” gives the most likely estimate four times the influence, reflecting real-world project uncertainty.

CAPM Predictive Plan-Based Methodologies Practice Question

This CAPM practice question tests your understanding of predictive plan-based methodologies. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

A project manager is creating the project schedule. The team estimates that the optimistic time for an activity is 10 days, the pessimistic time is 30 days, and the most likely time is 15 days. Using PERT three-point estimation, what is the expected duration?

Clue words in this question

Noticing these words before you look at the options changes how you read each choice.

  • Clue: "most likely"

    Why it matters: Probability qualifier — the question wants the most probable cause or outcome, not a guaranteed one. Eliminate low-probability options.

Question 1easymultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

16.67 days

The PERT three-point estimate formula is (Optimistic + 4×Most Likely + Pessimistic) / 6. Plugging in the values: (10 + 4×15 + 30) / 6 = (10 + 60 + 30) / 6 = 100 / 6 = 16.67 days. This weighted average gives more influence to the most likely estimate, reflecting a beta distribution.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • 16.67 days

    Why this is correct

    Correct calculation using PERT formula.

    Clue confirmation

    The clue word "most likely" in the question point toward this answer.

    Related concept

    Read the scenario before looking for a memorised answer.

  • 18.33 days

    Why it's wrong here

    This might result from using a different formula.

  • 20.00 days

    Why it's wrong here

    This is the average of optimistic and pessimistic.

  • 15.00 days

    Why it's wrong here

    This is just the most likely time.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates often use a simple arithmetic mean (average) instead of the weighted PERT formula, leading them to select 18.33 days (Option B).

Detailed technical explanation

How to think about this question

PERT (Program Evaluation and Review Technique) uses a beta distribution to model activity durations, where the formula (O + 4M + P)/6 approximates the mean. The standard deviation is (P - O)/6, which for this activity is (30-10)/6 = 3.33 days, allowing calculation of confidence intervals. In practice, this method is critical for high-uncertainty projects like software development or construction, where single-point estimates are unreliable.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the CAPM exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related CAPM practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free CAPM practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this CAPM question test?

Predictive Plan-Based Methodologies — This question tests Predictive Plan-Based Methodologies — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: 16.67 days — The PERT three-point estimate formula is (Optimistic + 4×Most Likely + Pessimistic) / 6. Plugging in the values: (10 + 4×15 + 30) / 6 = (10 + 60 + 30) / 6 = 100 / 6 = 16.67 days. This weighted average gives more influence to the most likely estimate, reflecting a beta distribution.

What should I do if I get this CAPM question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Are there clue words in this question I should notice?

Yes — watch for: "most likely". Probability qualifier — the question wants the most probable cause or outcome, not a guaranteed one. Eliminate low-probability options.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Keep practising

More CAPM practice questions

Last reviewed: Jun 11, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.