Courseiva

CAPM Predictive Plan-Based Methodologies Practice Question

Which THREE of the following are typically included in a project management plan (as opposed to project documents)?

⚠ Common exam trap

CAPM often tests the subtle distinction between project management plan components (subsidiary plans and baselines) and project documents (registers, logs, and records) — candidates frequently misclassify the stakeholder register or issue log as part of the plan.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Schedule management plan

The project management plan is composed of subsidiary management plans and baselines, so A (Schedule management plan), B (Scope management plan), and D (Risk management plan) are all correct because each is a formal subsidiary plan that describes how the respective knowledge area will be planned, executed, monitored, and controlled throughout the project. These plans are developed as part of the project management plan and are formally approved and controlled through integrated change control. By contrast, C (Stakeholder register) and E (Issue log) are project documents, not components of the project management plan; they are working records that are created and updated during project execution and are not part of the formal plan baselines or subsidiary plans.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Schedule management plan

    Why this is correct

    The schedule management plan is a subsidiary component of the project management plan, describing how the schedule is developed, monitored and controlled. Project documents, by contrast, include items such as the schedule baseline's supporting activity lists and duration estimates.

  • ✓

    Scope management plan

    Why this is correct

    The scope management plan is a subsidiary component of the project management plan, describing how scope is defined, validated and controlled. It belongs to the plan rather than the project documents, satisfying the stem's distinction between planning artefacts and supporting records.

  • ✗

    Stakeholder register

    Why it's wrong here

    The stakeholder register is a project document, not a component of the project management plan. It is tempting because stakeholder engagement planning sits inside the plan, but the register itself is produced by identify stakeholders and maintained as a separate project document.

  • ✓

    Risk management plan

    Why this is correct

    The risk management plan belongs in the project management plan because it defines how risk activities will be structured and performed, not the individual risk records themselves. This satisfies the stem's constraint of distinguishing plan components from project documents, where risk registers and reports reside.

  • ✗

    Issue log

    Why it's wrong here

    The issue log is a project document, not part of the project management plan. It is tempting because issue management is described within the plan's risk and communications components, yet the log itself is created and updated as a separate project document.

About these practice questions

This CAPM question is part of Courseiva's 451-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PMI exam blueprint

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.