CAPM Predictive Plan-Based Methodologies Practice Question
Which THREE of the following are typically included in a project management plan (as opposed to project documents)?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Schedule management plan
The correct answers are A, B, and D. The schedule management plan, scope management plan, and risk management plan are all subsidiary plans that are part of the project management plan. Options C (stakeholder register) and E (issue log) are project documents, not components of the project management plan.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Schedule management plan
Why this is correct
It describes how the schedule will be managed.
- ✓
Scope management plan
Why this is correct
It is a component of the project management plan.
- ✗
Stakeholder register
Why it's wrong here
The stakeholder register is a project document.
- ✓
Risk management plan
Why this is correct
It outlines risk management processes.
- ✗
Issue log
Why it's wrong here
The issue log is a project document, not a part of the plan.
Go deeper
Related to this question
About these practice questions
This CAPM question is part of Courseiva's 487-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →
JA
Written by Johnson Ajibi, MSc IT Security
Senior Network & Security Engineer · founder of Courseiva
This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.