Courseiva
Predictive Plan-Based MethodologiesmediumMultiple ChoiceObjective-mapped

CAPM Predictive Plan-Based Methodologies Practice Question

During the creation of the project schedule, a project manager needs to identify and document the logical relationships among activities. Which technique should be used?

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Precedence Diagramming Method (PDM)

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Program Evaluation and Review Technique (PERT)

    Why it's wrong here

    PERT is used for estimating activity durations with three-point estimates, not for dependencies.

  • Resource leveling

    Why it's wrong here

    Resource leveling addresses resource conflicts, not activity dependencies.

  • Precedence Diagramming Method (PDM)

    Why this is correct

    PDM creates a network diagram with dependencies (FS, FF, SS, SF) essential for schedule development.

  • Gantt chart

    Why it's wrong here

    A Gantt chart visualizes the schedule but does not explicitly model dependencies.

About these practice questions

One of 487 original CAPM practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.