- A
Submit a change request to the change control board (CCB).
This follows the formal change control process.
- B
Approve the change immediately and inform the team.
Why wrong: The project manager may not have authority; change control board approval is needed.
- C
Update the project charter to reflect the new feature.
Why wrong: The project charter is a high-level document; changes to scope go through change control.
- D
Implement the change since it is within the contingency reserves.
Why wrong: Even if within reserves, formal change control must be followed.
Quick Answer
The correct first step is to submit a change request to the change control board (CCB). This is because the change control process for scope changes in predictive projects mandates that all proposed modifications, even minor ones, must be formally documented and reviewed by the CCB before any action is taken. The project manager’s assessment of cost and schedule impact is part of the analysis, but it does not grant the authority to approve the change; the CCB holds that decision-making power. On the Certified Associate in Project Management CAPM exam, this scenario tests your understanding of the formal change control system and the distinction between analyzing an impact and obtaining approval. A common trap is assuming that minor changes within contingency reserves can be implemented directly, but the process requires submission regardless of size. Remember the mnemonic: “Assess, then request—never implement without the CCB’s behest.”
CAPM Predictive Plan-Based Methodologies Practice Question
This CAPM practice question tests your understanding of predictive plan-based methodologies. The scenario asks you to isolate a root cause — eliminate options that address a different problem before choosing. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.
During a predictive project's execution phase, a key stakeholder requests a change that adds a minor feature. The project manager assesses the impact and determines the change will increase cost by 5% and extend the schedule by two days, which is within the contingency reserves. What should the project manager do first?
Clue words in this question
Noticing these words before you look at the options changes how you read each choice.
Clue:
"first"Why it matters: Order matters here. You are being tested on which action comes before the others — not which action is generally useful.
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
Submit a change request to the change control board (CCB).
Option D is correct because the change control process requires submitting the change request to the change control board (CCB) for approval before implementation. Option A is wrong because implementing without approval bypasses change control. Option B is wrong because the project charter is not updated for minor changes; that is part of integrated change control. Option C is wrong because the project manager cannot unilaterally approve changes unless given authority; the CCB typically approves.
Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Submit a change request to the change control board (CCB).
Why this is correct
This follows the formal change control process.
Clue confirmation
The clue word "first" in the question point toward this answer.
Related concept
Read the scenario before looking for a memorised answer.
- ✗
Approve the change immediately and inform the team.
Why it's wrong here
The project manager may not have authority; change control board approval is needed.
- ✗
Update the project charter to reflect the new feature.
Why it's wrong here
The project charter is a high-level document; changes to scope go through change control.
- ✗
Implement the change since it is within the contingency reserves.
Why it's wrong here
Even if within reserves, formal change control must be followed.
Common exam traps
Common exam trap: answer the scenario, not the keyword
Many certification questions include familiar terms but test a specific constraint. Read the exact wording before choosing an answer that is generally true but wrong for this case.
Detailed technical explanation
How to think about this question
This question should be treated as a scenario, not a definition check. Identify the problem, the constraint and the best action. Then compare each option against those facts.
KKey Concepts to Remember
- Read the scenario before looking for a memorised answer.
- Find the constraint that changes the correct option.
- Eliminate answers that are true in general but not in this case.
- Use explanations to understand the rule behind the answer.
TExam Day Tips
- Underline the problem statement mentally.
- Watch for words such as best, first, most likely and least administrative effort.
- Review why wrong options are wrong, not only why the correct option is correct.
Key takeaway
Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.
Real-world example
How this comes up in practice
A practitioner preparing for the CAPM exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.
What to study next
Got this wrong? Here's your next step.
Identify which CAPM exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.
- →
Predictive Plan-Based Methodologies — study guide chapter
Learn the concepts, then practise the questions
- →
Predictive Plan-Based Methodologies practice questions
Targeted practice on this topic area only
- →
All CAPM questions
503 questions across all exam domains
- →
Certified Associate in Project Management CAPM study guide
Full concept coverage aligned to exam objectives
- →
CAPM practice test guide
How to use practice tests most effectively before exam day
Related practice questions
Related CAPM practice-question pages
Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.
Agile Frameworks and Methodologies practice questions
Practise CAPM questions linked to Agile Frameworks and Methodologies.
Project Management Fundamentals and Core Concepts practice questions
Practise CAPM questions linked to Project Management Fundamentals and Core Concepts.
Predictive Plan-Based Methodologies practice questions
Practise CAPM questions linked to Predictive Plan-Based Methodologies.
Business Analysis Frameworks practice questions
Practise CAPM questions linked to Business Analysis Frameworks.
CAPM fundamentals practice questions
Practise CAPM questions linked to CAPM fundamentals.
CAPM scenario practice questions
Practise CAPM questions linked to CAPM scenario.
CAPM troubleshooting practice questions
Practise CAPM questions linked to CAPM troubleshooting.
Practice this exam
Start a free CAPM practice session
Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.
FAQ
Questions learners often ask
What does this CAPM question test?
Predictive Plan-Based Methodologies — This question tests Predictive Plan-Based Methodologies — Read the scenario before looking for a memorised answer..
What is the correct answer to this question?
The correct answer is: Submit a change request to the change control board (CCB). — Option D is correct because the change control process requires submitting the change request to the change control board (CCB) for approval before implementation. Option A is wrong because implementing without approval bypasses change control. Option B is wrong because the project charter is not updated for minor changes; that is part of integrated change control. Option C is wrong because the project manager cannot unilaterally approve changes unless given authority; the CCB typically approves.
What should I do if I get this CAPM question wrong?
Identify which CAPM exam domain this question belongs to, then review the specific concept being tested. Practise related questions in that domain and focus on understanding why each wrong answer is tempting — not just why the correct answer is right.
Are there clue words in this question I should notice?
Yes — watch for: "first". Order matters here. You are being tested on which action comes before the others — not which action is generally useful.
What is the key concept behind this question?
Read the scenario before looking for a memorised answer.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Same concept, more angles
3 more ways this is tested on CAPM
These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.
Variation 1. During project execution, a key stakeholder requests a change that will increase the project scope. The project manager evaluates the impact and determines it will require additional budget and time. What is the first step the project manager should take?
easy- A.Reject the change due to budget and time constraints
- ✓ B.Submit a change request to the change control board
- C.Implement the change and document it later
- D.Approve the change because the stakeholder is key
Why B: In predictive (waterfall) project management, any change that impacts scope, budget, or schedule must follow the formal integrated change control process. The project manager's first step after evaluating the impact is to submit a change request to the change control board (CCB) for approval or rejection. This ensures that all changes are documented, assessed for risks, and aligned with the project baseline before implementation.
Variation 2. During project execution, a key stakeholder requests a change that will increase the project scope. The project manager evaluates the impact and determines it will require additional budget and time. What should the project manager do first?
medium- A.Implement the change and update the project plan
- ✓ B.Submit a change request to the change control board
- C.Update the project baseline immediately
- D.Reject the change because it impacts the baseline
Why B: In predictive (waterfall) project management, any change that impacts scope, budget, or schedule must follow a formal change control process. The project manager first assesses the impact, then submits a change request to the Change Control Board (CCB) for approval before any action is taken. Implementing the change or updating baselines without CCB approval violates the control scope process defined in the PMBOK Guide.
Variation 3. In a predictive project, the project sponsor requests a scope change that will significantly increase the project cost. The project manager should FIRST:
hard- A.Reject the change as it impacts budget
- ✓ B.Evaluate the impact of the change on the project constraints
- C.Update the project charter
- D.Implement the change immediately
Why B: When a scope change is requested, the project manager must first evaluate the impact on project constraints (cost, schedule, quality, etc.) before proceeding. Updating the charter or rejecting the change without evaluation is premature.
Keep practising
More CAPM practice questions
- Which THREE factors should a business analyst consider when selecting an elicitation technique for a project?
- Drag and drop the steps for conducting a procurement process in the correct order.
- Drag and drop the steps for controlling project changes according to the integrated change control process.
- Drag and drop the steps for managing project quality in the correct order.
- Drag and drop the steps for closing a project phase or project in the correct order.
- Drag and drop the steps for managing project communications in the correct order.
Last reviewed: Jun 24, 2026
This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.