Courseiva

CAPM Practice Question: Project Management Fundamentals and Core Concepts

A project manager is developing the project management plan for a complex software development project. The project manager needs to ensure that the plan includes all necessary subsidiary plans and baselines. Which three of the following are components of the project management plan? (Choose three.)

⚠ Common exam trap

A common mix-up: candidates confuse project inputs like the business case and statement of work with components of the project management plan.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Cost baseline

The project management plan integrates and consolidates all subsidiary plans and baselines. Key components include the scope management plan, which outlines how scope will be managed; the cost baseline, which is the approved time-phased budget; and the schedule baseline, which is the approved schedule used for performance measurement. The project statement of work and business case are inputs to project charter development, not components of the plan.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✓

    Cost baseline

    Why this is correct

    The cost baseline is a time-phased budget that is used to measure, monitor, and control overall cost performance on the project. It is a component of the project management plan and is developed as part of the Cost Management knowledge area.

  • ✓

    Schedule baseline

    Why this is correct

    The schedule baseline is the approved version of the schedule model that is used to compare actual performance to planned performance. It is a component of the project management plan and is critical for schedule control.

  • ✗

    Project statement of work

    Why it's wrong here

    The project statement of work (SOW) is a narrative description of products, services, or results to be delivered by the project. It is an input to the Develop Project Charter process, not a component of the project management plan. The SOW is provided by the customer or sponsor.

  • ✓

    Scope management plan

    Why this is correct

    The scope management plan is a subsidiary plan that describes how the project scope will be defined, developed, monitored, controlled, and validated. It is a component of the project management plan and is essential for managing scope throughout the project lifecycle.

  • ✗

    Business case

    Why it's wrong here

    The business case is a documented economic feasibility study used to establish the validity of the benefits of a selected component lacking sufficient definition. It is an input to the Develop Project Charter process, not a component of the project management plan. The business case justifies the project but is not part of the plan.

About these practice questions

This CAPM question is part of Courseiva's 451-question bank — original exam-style content with full explanations and wrong-answer analysis, never real exam questions or exam dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PMI exam blueprint

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.