Courseiva

CAPM Predictive Plan-Based Methodologies Practice Question

A project manager is reviewing the project's cost performance. The actual cost (AC) is $50,000, the earned value (EV) is $45,000, and the planned value (PV) is $60,000. What is the cost variance (CV)?

⚠ Common exam trap

A common mix-up: candidates confuse cost variance (CV = EV - AC) with schedule variance (SV = EV - PV) or incorrectly subtracting AC from EV, leading candidates to pick $5,000 or -$15,000.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

-$5,000

Cost variance (CV) is calculated as EV minus AC. Here, EV = $45,000 and AC = $50,000, so CV = $45,000 - $50,000 = -$5,000. A negative CV indicates the project is over budget, which matches option C.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    $5,000

    Why it's wrong here

    $5,000 is the magnitude of the variance but omits the negative sign, since EV ($45,000) is below AC ($50,000), indicating overspend. It is tempting because the arithmetic difference is right, and positive cost variance genuinely occurs when earned value exceeds actual cost.

  • ✗

    -$15,000

    Why it's wrong here

    -$15,000 is EV minus PV ($45,000 minus $60,000), which is the schedule variance, not the cost variance. It is tempting because both formulas subtract two earned-value metrics, and a negative result correctly signals behind-schedule performance, but cost variance uses AC.

  • ✓

    -$5,000

    Why this is correct

    Cost variance is EV minus AC, so $45,000 − $50,000 = −$5,000. The negative sign satisfies the stem's cost performance review: the project has spent more than the value earned, indicating an overrun of $5,000 against the actual cost constraint.

  • ✗

    $10,000

    Why it's wrong here

    Cost variance is EV minus AC, giving $45,000 minus $50,000, which equals -$5,000, not $10,000. The figure $10,000 is tempting because it is the difference between planned value and actual cost, a comparison that belongs to schedule or budget reporting rather than cost variance.

About these practice questions

Courseiva writes every CAPM question from scratch — 451 in total, each with an explanation and a wrong-answer breakdown. None are copied from real exams or dumps. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.