Courseiva

CAPM Predictive Plan-Based Methodologies Practice Question

A project manager is leading a predictive project to implement a new enterprise resource planning (ERP) system. During the Plan Quality Management process, the project manager is identifying quality requirements and documenting how the project will demonstrate compliance. Which two of the following are inputs to this process? (Choose two.)

⚠ Common exam trap

The trap here is selecting outputs from other quality processes, such as quality control measurements, which are not inputs to Plan Quality Management.

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

✓

Stakeholder register

Plan Quality Management involves identifying quality requirements and documenting how the project will comply. Its inputs include the project charter, which provides high-level objectives, and the stakeholder register, which identifies those with quality interests. Quality control measurements, work performance information, and verified deliverables are outputs of execution or monitoring processes and are not available during planning. Thus, the project charter and stakeholder register are the correct inputs.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • ✗

    Verified deliverables

    Why it's wrong here

    Verified deliverables are an output of Control Quality and an input to Validate Scope. They represent deliverables that have been completed and checked for correctness. They are not inputs to Plan Quality Management, which is performed during planning before any deliverables are produced. Therefore, verified deliverables are not relevant to this process.

  • ✗

    Quality control measurements

    Why it's wrong here

    Quality control measurements are an output of the Control Quality process and are used as an input to Manage Quality. They are not an input to Plan Quality Management because they represent results of quality control activities that occur during execution. In this planning phase, such measurements do not yet exist, so they cannot be an input to Plan Quality Management.

  • ✗

    Work performance information

    Why it's wrong here

    Work performance information is an input to Monitor and Control Project Work and other monitoring processes, not Plan Quality Management. It is derived from work performance data and provides status on project activities. Since Plan Quality Management is a planning process that occurs before execution, work performance information is not available and thus not an input here.

  • ✓

    Stakeholder register

    Why this is correct

    The stakeholder register is an input to Plan Quality Management as it identifies stakeholders who have a specific interest in or influence over quality. For the ERP project, key stakeholders such as the finance department or IT security may have quality requirements. Understanding their needs helps the project manager define quality standards and compliance approaches, so the stakeholder register is a correct input.

  • ✓

    Project charter

    Why this is correct

    The project charter is an input to Plan Quality Management because it provides high-level project information, including measurable project objectives and success criteria. These elements help the project manager identify quality requirements and expectations. In this ERP implementation, the charter may specify performance metrics or compliance standards that shape the quality management plan, making it a valid input.

About these practice questions

One of 451 original CAPM practice questions on Courseiva, each with a full explanation and wrong-answer analysis — not exam dumps or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

JA

Written and reviewed by Johnson Ajibi, MSc IT Security

Senior Network & Security Engineer · founder of Courseiva

Last reviewed September 2026 · checked against the official PMI exam blueprint

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.