Question 133 of 487
CAPM Practice Question: Project Management Fundamentals and Core Concepts
Which THREE of the following are characteristics of a project?
Answer choices
Why each option matters
Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.
Correct answer & explanation
✓
Progressive elaboration
Options A, C, and D are correct because projects are temporary (C), unique (D), and progressively elaborated (A). Option B (Repetitive) and option E (Ongoing) describe operations, not projects.
Answer analysis
Option-by-option breakdown
For each option: why learners choose it and why it is or isn't the right answer here.
- ✓
Progressive elaboration
Why this is correct
Projects are developed in steps and become more detailed over time.
- ✗
Repetitive
Why it's wrong here
Repetitive tasks are characteristic of operations.
- ✓
Temporary
Why this is correct
Projects have a defined start and end.
- ✓
Unique
Why this is correct
Each project creates a unique product or service.
- ✗
Ongoing
Why it's wrong here
Ongoing indicates operations, not projects.
About these practice questions
Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →
Last reviewed: Jun 24, 2026
This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.
Question Discussion
Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.
Sign in to join the discussion.