Question 176 of 503
Project Management Fundamentals and Core ConceptsmediumMultiple ChoiceObjective-mapped

Quick Answer

The answer is to analyze the impact on project constraints and submit a change request. This is the correct first step because the Integrated Change Control process requires a formal impact analysis before any change can be evaluated, ensuring the project manager understands how the new feature will affect scope, time, cost, and quality. On the CAPM exam, this tests your knowledge of the change control first step impact analysis, which is a common trap where students mistakenly jump to updating the project plan or implementing the change immediately. Instead, remember that no work begins until the change request is submitted and approved by the CCB. A useful memory tip is “Analyze before you authorize”—always assess the triple constraint impact first to prevent scope creep.

CAPM Practice Question: Project Management Fundamentals and Core Concepts

This CAPM practice question tests your understanding of project management fundamentals and core concepts. Read the scenario carefully and evaluate each option against the stated constraints before committing to an answer. After answering, compare your reasoning against the explanation and wrong-answer breakdown below. Once you have made your selection, read the full explanation to reinforce the concept and understand why each distractor is designed to mislead on exam day.

A project manager is leading a software development project. The sponsor has requested a new feature that was not part of the original scope. The project manager assesses that adding this feature will require additional resources and will extend the timeline by two weeks. What should the project manager do first?

Clue words in this question

Noticing these words before you look at the options changes how you read each choice.

  • Clue: "first"

    Why it matters: Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

Question 1mediummultiple choice
Full question →

Answer choices

Why each option matters

Answer the question above first, then reveal the full breakdown to understand why each option is right or wrong.

Correct answer & explanation

Analyze the impact on the project constraints and submit a change request.

The correct first step is to analyze the impact on the project constraints (scope, time, cost, quality) and submit a formal change request. This follows the Integrated Change Control process, ensuring the sponsor and change control board (CCB) evaluate the trade-offs before any work begins. In software development, adding a feature without analysis risks scope creep and uncontrolled budget or schedule deviations.

Key principle: Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Answer analysis

Option-by-option breakdown

For each option: why learners choose it and why it is or isn't the right answer here.

  • Refuse the request because it is out of scope.

    Why it's wrong here

    A project manager should not refuse without analysis; a change request process should be followed.

  • Analyze the impact on the project constraints and submit a change request.

    Why this is correct

    The PM should analyze impact and then submit a change request for approval.

    Clue confirmation

    The clue word "first" in the question point toward this answer.

    Related concept

    Read the scenario before looking for a memorised answer.

  • Instruct the team to implement the feature and track extra time as overtime.

    Why it's wrong here

    Implementing without approval violates change control processes.

  • Immediately update the project schedule and budget.

    Why it's wrong here

    Changes should go through formal change control before updating baselines.

Common exam traps

Common exam trap: answer the scenario, not the keyword

The trap here is that candidates confuse a sponsor's authority with the need for formal change control, assuming the sponsor can bypass the change request process, but the PM must still follow the defined change management procedures regardless of who makes the request.

Detailed technical explanation

How to think about this question

In the CAPM framework, the Perform Integrated Change Control process requires that all change requests be documented, analyzed for impact on the triple constraint (scope, time, cost), and approved or rejected by the CCB. A real-world scenario: a sponsor requests a new API endpoint; the PM must assess how it affects the existing sprint backlog, resource allocation, and release date before submitting a change request. This prevents the common pitfall of 'gold-plating' where unauthorized features degrade project performance.

KKey Concepts to Remember

  • Read the scenario before looking for a memorised answer.
  • Find the constraint that changes the correct option.
  • Eliminate answers that are true in general but not in this case.

TExam Day Tips

  • Watch for words such as best, first, most likely and least administrative effort.
  • Review why wrong options are wrong, not only why the correct option is correct.

Key takeaway

Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option.

Real-world example

How this comes up in practice

A practitioner preparing for the CAPM exam encounters this exact type of scenario on the job. The correct answer here is not the most general option — it is the best answer for the specific constraint described. Answer the scenario, not the keyword: identify the specific constraint before choosing the most familiar-sounding option. Real exam questions reward reading the full scenario before eliminating options, because the constraint defines which answer fits.

What to study next

Got this wrong? Here's your next step.

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Related practice questions

Related CAPM practice-question pages

Use these pages to review the topic behind this question. This is how one missed question becomes focused revision.

Practice this exam

Start a free CAPM practice session

Short sessions build daily habit. Longer sessions build exam-day stamina. Try a timed session to simulate real conditions.

FAQ

Questions learners often ask

What does this CAPM question test?

Project Management Fundamentals and Core Concepts — This question tests Project Management Fundamentals and Core Concepts — Read the scenario before looking for a memorised answer..

What is the correct answer to this question?

The correct answer is: Analyze the impact on the project constraints and submit a change request. — The correct first step is to analyze the impact on the project constraints (scope, time, cost, quality) and submit a formal change request. This follows the Integrated Change Control process, ensuring the sponsor and change control board (CCB) evaluate the trade-offs before any work begins. In software development, adding a feature without analysis risks scope creep and uncontrolled budget or schedule deviations.

What should I do if I get this CAPM question wrong?

Identify which exam domain this question belongs to, review the core concept, then practise similar questions from the same domain.

Are there clue words in this question I should notice?

Yes — watch for: "first". Order matters here. You are being tested on which action comes before the others — not which action is generally useful.

What is the key concept behind this question?

Read the scenario before looking for a memorised answer.

About these practice questions

Courseiva creates original exam-style practice questions with explanations and wrong-answer analysis. It does not publish real exam questions, exam dumps, or protected exam content. Learn why practice questions differ from exam dumps →

How Courseiva writes practice questions · Editorial policy

Same concept, more angles

1 more ways this is tested on CAPM

These questions test the same concept from different angles. Work through them to make sure you can recognise it however the exam phrases it.

Variation 1. During project execution, a key stakeholder requests a new feature that was not included in the approved scope. What should the project manager do first?

easy
  • A.Perform a change impact analysis
  • B.Escalate to the project sponsor for decision
  • C.Inform the stakeholder that the scope is frozen
  • D.Add the feature to the next iteration

Why A: Option B is correct because the project manager should assess the impact of the change on the project constraints before taking any action. Option A is wrong because implementing without analysis violates change control. Option C is wrong because rejecting without analysis is not proactive. Option D is wrong because the sponsor may not be involved in day-to-day changes.

Last reviewed: Jun 11, 2026

Question Discussion

Share a tip, memory trick, or ask about the reasoning behind this question. Do not post real exam questions, leaked content, braindumps, or copyrighted exam material. Comments are moderated and may be removed without notice.

Loading comments…

Sign in to join the discussion.

This CAPM practice question is part of Courseiva's free PMI certification practice question bank. Courseiva provides original exam-style practice questions with explanations, topic-based practice, mock exams, readiness tracking, and study analytics to help learners prepare for the CAPM exam.